File #: 19-0956    Name: Reallocation of MCDC Funds
Type: Agenda Item Status: Agenda Ready
In control: Parks, Recreation, and Open Space Advisory Board
On agenda: 11/14/2019 Final action:
Title: Consider/Discuss/Act on Making a Recommendation to the McKinney Community Development Corporation to Reallocate Existing Funds in order to Complete Substantial Renovations to the Senior Recreation Center, Improvements to Various Neighborhood Parks, the Purchase of a Parks & Recreation Bus, and the Purchase of Outdoor Workout Equipment

Title

Consider/Discuss/Act on Making a Recommendation to the McKinney Community Development Corporation to Reallocate Existing Funds in order to Complete Substantial Renovations to the Senior Recreation Center, Improvements to Various Neighborhood Parks, the Purchase of a Parks & Recreation Bus, and the Purchase of Outdoor Workout Equipment

 

Summary

COUNCIL GOAL:                     Enhance the Quality of Life in McKinney

(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)

(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)

(5E: Develop sustainable quality of life improvements within the City of McKinney)

MEETING DATE:                     November 14, 2019

DEPARTMENT:                      Parks & Recreation

CONTACT:                       Michael Kowski, Director of Parks and Recreation

 

RECOMMENDED PROS BOARD ACTION:                     

                     Recommend to the MCDC to approve the reallocation of existing funding.

 

ITEM SUMMARY: 

                     The Parks and Recreation Department is requesting to reallocate existing MCDC funds in the amount of $3,579,583 to expedite the delivery of certain enhancements across the McKinney parks system. This item does not include any new funding requests.

 

BACKGROUND INFORMATION: 

                     The MCDC approved $5,500,000 in funding for this FY19-20 to implement various elements of the Parks Master Plan. MCDC also approved funding for other Parks projects in 2016, 2017 and 2018 that are available for reallocation.

 

                     Part of the approved FY19-20 funding included $1,150,000 in Umbrella Funding, for a total amount of $1,375,000, for reallocation to various projects as needed.

 

                     To fund substantial renovations to the Senior Recreation Center (PK4384), this request will reallocate $1,000,000 from Land Acquisition (PK1701) and $1,000,000 from Umbrella Funding (PK4399) to increase the total project budget to $3,500,000. This project is in the final design phase with construction anticipated to commence in Q1 of 2020.  

 

                     To fund outdoor workout equipment, this request will reallocate $150,000 of the FY19-20 Umbrella Funding. This equipment is proposed to be installed at Bonnie Wenk Park, with future installation locations to be determined.

 

                     To fund a new Parks & Recreation Bus, this request will reallocate $175,000 of the remaining $225,000 of FY18-19 Umbrella Funding (PK4399). 

 

                     To fund an update to the 2017 Parks Master Plan Update (PK2040), this request will reallocate $50,000 of the remaining $225,000 of FY18-19 Umbrella Funding (PK4399). The total project budget is $250,000, and will include updates to the general plan, the creation of a comprehensive trails plan with wayfinding, and the development of a sponsorship program to offset capital and operational expenses, as well as other updates.

 

                     To fund improvements to various Neighborhood Parks, this request will reallocate $1,204,583 from Gray Branch (PK2206) for a total budget of $1,204,583. This funding will be used for design services and some construction work, with primary construction funding coming from a potential mid-2020 bond issuance.

 

                     The total amount to be reallocated is $3,579,583.

 

FINANCIAL SUMMARY:

                     Amending Project 16-08 and Project 17-05 amounts for Gray Branch (PK2206) to reallocate $1,204,583 of $1,270,000 (Total allocated was $770,000 from 17-05; 500,000 from 16-08) to Park Renovations (PK1831); amending Project 16-08 for Land Acquisition (PK1701) to reallocate $1,000,000 of $1,279,329 to Senior Recreation Center (PK4394); amending  Project 18-08 (Umbrella Fund) to reallocate $175,000 of $225,000 for Purchase of Parks and Recreation Bus; amending Project 18-08 (Umbrella Fund) to reallocate $50,000 of $225,000 to Parks Master Plan Update (PK2040); amending Project 19-10 (Umbrella Fund)  to reallocate $1,000,000 of $1,150,000 to Senior Recreation Center (PK4394); and $150,000 of $1,150,000 for the purchase of outdoor workout equipment.