File #: 20-0151    Name: Cottonwood Park Renovation Project
Type: Agenda Item Status: Agenda Ready
In control: Parks, Recreation, and Open Space Advisory Board
On agenda: 2/13/2020 Final action:
Title: Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of the Cottonwood Park Renovation Project

Title

Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of the Cottonwood Park Renovation Project

 

Summary

 

COUNCIL GOAL:   Enhance the Quality of Life in McKinney                                                               

(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)

(5B: Develop Parks strategy to preserve green space for future park land)

(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)

(5E: Develop sustainable quality of life improvements within the City of McKinney)

 

MEETING DATE:    February 13, 2020

 

DEPARTMENT:                      Parks and Recreation

 

CONTACT:                       Michael Kowski, Director of Parks and Recreation

 

 

RECOMMENDED ACTION:                     

                     Approve the recommendation to City Council.

 

ITEM SUMMARY: 

                     The renovation of Cottonwood Park includes new play equipment, pavilions, sport-court, shade structures, on and off street parking, splash feature, pedestrian connectivity and landscaping.  

                     City staff worked with Kimley-Horn on preparing the construction plans and specifications as needed for project bidding.

 

                     The project includes a base bid and 4 alternates:

 

o                     Alternate 1: Sport court shade structure

 

o                     Alternate 2: Playground shade structure

 

o                     Alternate 3: Shade structures along McMakin Street

 

o                     Alternate 4: LED lighting along the stone benches

 

                     Staff declined to accept

 

                     Staff recommends awarding the construction bid to North Rock Construction, LLC in an amount of $2,820,520.31 (includes base bid + Alternates 1-3).

 

BACKGROUND INFORMATION: 

                     A total of 10 bids were received.

 

                     North Rock Construction has completed projects for the City of McKinney in the past, including Dr. Mack Hill Park and various trail projects.

             

                     If approved, construction should begin in March with a 273 day contract schedule.

 

FINANCIAL SUMMARY: 

                     The Cottonwood Park Renovation Project (PK1737) is a FY19-20 Capital Improvements Program funded by MCDC funds and Parkland Dedication Funds Zone 4. 

 

                     Upon approval of this item, $125,679 remains in the project budget.