Title
Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with Brown & Gay Engineers, Inc., for Engineering Design Services for the Reconstruction of Cole Street from Bass Street to College Street, and Any Necessary Supplemental Agreements
 
Summary
 
MEETING DATE:      December 1, 2014
 
DEPARTMENT:      Development Services / Engineering
 
CONTACT:      Gary Graham, P.E., CIP and Transportation Engineering Manager
      Carla Easton, P.E., Civil Engineer
 
 
RECOMMENDED CITY COUNCIL ACTION:
·      Approval of Resolution.
 
ITEM SUMMARY:
·      This Resolution authorizes a contract with Brown & Gay Engineers, Inc. (BGE), to provide consulting engineering services for the design of Cole Street from Bass Street to College Street for an amount not to exceed $230,000.
·      The project includes the reconstruction of water lines, sanitary sewers, storm drains, street paving, and sidewalks.
 
BACKGROUND INFORMATION:
·      BGE submitted a response to RFQ 13-09 for Minor Roadway Design.  They were one of ten firms shortlisted by City Council on February 5, 2013.
·      BGE was selected for this project based on their experience with similar projects and their performance on other City of McKinney projects.
·      BGE submitted a proposal for this project in the amount of $202,265.  Their scope includes the following elements:
o      Topographical and boundary survey;
o      Design of infrastructure improvements including:
·      2260 feet of water line
·      2045 feet of sanitary sewer
·      930 feet of storm drain, with potential modifications to existing headwalls
·      2000 feet of concrete street paving
·      Continuous sidewalk and curb ramps for ADA compliance
o      Environmental investigation and project documentation;
o      Bid phase services; and
o      Construction phase services.
·      The estimated construction cost of the project is $1,385,000.
·      Design of this project is anticipated to take six months to complete.  Construction is anticipated to begin in October 2015 and to be complete by July 2016.
FINANCIAL SUMMARY:
·      This Resolution authorizes a design contract and any necessary supplemental agreements with Brown & Gay Engineers, Inc., for an amount not to exceed $230,000.
·      Funding for this contract is included in the Capital Improvements Program (CO9151 in the amount of $1,700,000).   
·      The funding sources for CO9151 will be split 80% from the street construction fund and 20% from the utility construction fund.
·      With the approval of this item, $1,470,000 will remain in project CO9151.  
 
BOARD OR COMMISSION RECOMMENDATION: