File #: 19-0707    Name: Stacy Road Lanes 5 and 6 (Custer Road to Ridge Road) Design Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 8/20/2019 Final action: 8/20/2019
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Atkins North America, Inc. for Professional Engineering Design Services for the Stacy Road Lanes 5 and 6 (Custer Road to Ridge Road) Project (ST3212) and Authorizing Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Atkins North America, Inc. for Professional Engineering Design Services for the Stacy Road Lanes 5 and 6 (Custer Road to Ridge Road) Project (ST3212) and Authorizing Any Necessary Supplemental Agreements

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance available resources to accommodate the growth and maintenance needs of the city)

 

MEETING DATE:                     August 20, 2019

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Nick Ataie, PE, Engineering CIP Manager

                     Aniswarie Kanamazina, PE, CIP Engineer

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes the City Manager to execute a contract in the amount of $758,084.10, as well as all required supplemental agreements thereto, with Atkins North America, Inc. for professional consulting engineering services for the Stacy Road Lanes 5 and 6 (Custer Road to Ridge Road) Project (ST3212), for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $835,000.

 

BACKGROUND INFORMATION:

                     The FY19 budget includes funding for various citywide intersections capacity improvements along Stacy Road under Capital Improvement Project ST3212, Stacy Road Lanes 5 and 6 (Custer Road to Ridge Road) Project.

                     Traffic volumes on this section of Stacy Road currently exceed 20,000 vehicles per day, which is approaching capacity for a four-lane roadway.

                     This project will include the widening of Stacy Road within the median from four lanes to six lanes between Custer Road and Ridge Road, a distance of approximately 10,700 linear feet. It will also include various intersection/turn lane improvements, traffic signal modifications, and installation of new traffic signal at McKinney Ranch Parkway intersection.

                     Atkins North America, Inc. submitted a response to RFQ 18-45 for On-Call Roadway Design Services. They were one of twelve firms shortlisted by City Council on October 2, 2018.

                     Staff has negotiated a scope and fee from Atkins North America, Inc. for professional consulting engineering services and construction administration services in the amount of $758,084.10.

                     The preliminary opinion of probable construction cost is $4,765,000.

                     The fee for basic services is $522,525.00 (10.9% of the engineer’s opinion of probable cost of construction) and the fee for special services is $235,559.10 (4.9% of the engineer’s opinion of probable cost of construction).

                     Special services typically include survey for design, franchise utility coordination, subsurface utility engineering, preparation of necessary right-of-way and/or easements, environmental investigations, and limited construction administration.

                     Staff is requesting approval of a not to exceed (NTE) amount of $835,000 in the event minor adjustments in the project scope are required during the design or construction administration services provided.

                     Design of this project is anticipated to take approximately 11 months to complete with construction estimated to begin as soon as Fall 2020.

 

FINANCIAL SUMMARY:

                     This Resolution authorizes a design contract and any necessary supplemental agreements with Atkins North America, Inc. for an amount not to exceed $835,000.

                     Funds are available in the Capital Improvements Program Project ST3212.

                     With the approval of this item, $32,073.00 will remain in ST3212.

                     Funding for the construction phase is planned to be issued in late 2019 from 2015 voter-authorized bonds (streets).

 

 