File #: 14-373    Name: Lake Forest 5 & 6 - Design
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 4/15/2014 Final action: 4/15/2014
Title: Consider/Discuss/Act on a Resolution Authorizing the Deputy City Manager to Execute a Contract and All Necessary Supplemental Agreements with Civil Consulting Group, PLLC, for Engineering Design Services for Lake Forest Drive Lanes 5 and 6 from SH 121 to McKinney Ranch Parkway
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the Deputy City Manager to Execute a Contract and All Necessary Supplemental Agreements with Civil Consulting Group, PLLC, for Engineering Design Services for Lake Forest Drive Lanes 5 and 6 from SH 121 to McKinney Ranch Parkway

 

Summary

 

MEETING DATE:                     April 15, 2014

 

DEPARTMENT:                     Development Services/Engineering

 

CONTACT:                     Danny Still, PE, CIP Engineer
Gary Graham, PE, PTOE, CIP & Transportation Engineering Manager

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes a contract and all necessary supplemental agreements with Civil Consulting Group, PLLC, for engineering design services for Lake Forest Drive lanes 5 and 6 from SH 121 to McKinney Ranch Parkway for an amount not to exceed $190,000.

 

BACKGROUND INFORMATION:

                     The additional lanes are needed because of increasing traffic volumes in the southwest quadrant of McKinney.

                     The two new lanes will be constructed in the existing median.

                     Civil Consulting Group submitted a response to RFQ 13-09 for Minor Roadway Design.  They were one of ten firms shortlisted by City Council on February 5, 2013.

                     Civil Consulting Group was selected for this project based on their experience with similar projects and their performance on other City of McKinney projects.

                     Civil Consulting Group submitted a proposal for this project in the amount of $169,141.42.  Their scope includes the following elements:

o                     Topographical and boundary survey;

o                     Design of the new travel lanes and modification of existing medians along Lake Forest Drive;

o                     Design of a right turn lane and a second left turn lane on eastbound McKinney Ranch Parkway at Lake Forest Drive;

o                     Design of a second left turn lane on northbound Lake Forest Drive at McKinney Ranch Parkway;

o                     Modification of the storm drainage systems along the project to accommodate the proposed improvements;

o                     Design of the modifications to the traffic signals at McKinney Ranch Parkway and SH 121;

o                     Coordination with TxDOT and franchise utilities;

o                     Bid phase services; and

o                     Construction phase services.

                     The estimated construction cost of the project is $1,512,000.

                     Design of this project is anticipated to take six months to complete.  Construction is anticipated to begin in January 2015 and to be complete by June 2015.

 

FINANCIAL SUMMARY:

                     This Resolution authorizes a design contract and all necessary supplemental agreements with Civil Consulting Group for an amount not to exceed $190,000.

                     Funding for this contract is included in the Capital Improvements Program (ST3209).

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A