File #: 13-1017    Name: Virginia 5 & 6 - Design Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 10/1/2013 Final action: 10/1/2013
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Halff Associates, Inc., for Engineering Design Services for Virginia Parkway Lanes 5 and 6 from Bellegrove Drive to US 75 and Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Halff Associates, Inc., for Engineering Design Services for Virginia Parkway Lanes 5 and 6 from Bellegrove Drive to US 75 and Any Necessary Supplemental Agreements
 
Summary
 
MEETING DATE:      October 1, 2013
 
DEPARTMENT:      Development Services / Engineering
 
CONTACT:      Matt Richardson, P.E., CIP Manager
      Carla Easton, P.E., Civil Engineer
 
 
RECOMMENDED CITY COUNCIL ACTION:
·      Approval of Resolution.
 
ITEM SUMMARY:
·      This Resolution authorizes a contract with Halff Associates, Inc., to provide consulting engineering services for the design of lanes 5 and 6 on Virginia Parkway from Bellegrove Drive to US 75 for an amount not to exceed $1,300,000.
 
BACKGROUND INFORMATION:
·      Traffic volumes on Virginia Parkway currently exceed 25,000 vehicles per day, which is near capacity for a four-lane roadway, and will continue to grow as in-fill development continues along the corridor.  
·      This project will include the widening of Virginia Parkway from four lanes to six lanes between Bellegrove Drive and US 75, a distance of approximately 9,500 feet.  It will also include storm sewer modifications related to the roadway widening and water and sewer improvements at various locations within the project limits.
·      This segment of Virginia Parkway is currently designated FM 3038 and is under the jurisdiction of the Texas Department of Transportation; however, City Council authorized the City Manager to request the removal of FM 3038 from the state highway system on August 20, 2013.  
·      Halff submitted a response to RFQ 13-08 for Major Roadway Design.  They were one of eight firms shortlisted by City Council on February 5, 2013.  
·      Staff interviewed three firms from the short list specifically for this project.  Halff was selected from this group based on their understanding of the project concepts and their experience with similar projects in the DFW Metroplex.
·      Halff submitted a proposal for this project in the amount of $1,196,600.  Their scope includes floodplain analysis at Wilson Creek and Jean's Creek; right-of-way and easement mapping; roadway, bridge, drainage, and utility design; and construction administration.  
·      Design and right-of-way acquisition for this project is anticipated to take approximately 18 months to complete.  Construction is anticipated to begin in Summer 2015 and to be complete by Summer 2016.  
 
FINANCIAL SUMMARY:
·      This Resolution authorizes a design contract and any necessary supplemental agreements with Halff, for an amount not to exceed $1,300,000.
·      Funding for this contract is included in the Capital Improvements Program (ST1219 & WA9145).
·      A separate Resolution to authorize a Local Project Advance Funding Agreement with the Texas Department of Transportation for the use of Regional Toll Revenue funding for this project will be presented to City Council at a later date.  
 
BOARD OR COMMISSION RECOMMENDATION:
·      N/A