File #: 14-329    Name: Stacy 5 & 6 - Construction
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 4/1/2014 Final action: 4/1/2014
Title: Consider/Discuss/Act on a Resolution Authorizing the Deputy City Manager to Execute a Contract and All Necessary Change Orders with Tiseo Paving Company for the Construction of Stacy Road Lanes 5 & 6 from Ridge Road to SH 121 and a Right Turn Lane from SH 121 to Ridge Road
Attachments: 1. Resolution, 2. Award Recommendation Letter, 3. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the Deputy City Manager to Execute a Contract and All Necessary Change Orders with Tiseo Paving Company for the Construction of Stacy Road Lanes 5 & 6 from Ridge Road to SH 121 and a Right Turn Lane from SH 121 to Ridge Road

 

Summary

 

MEETING DATE:                     April 1, 2014

 

DEPARTMENT:                     Development Services / Engineering

 

CONTACT:                     Gary Graham, PE, CIP Manager

                     Danny Still, PE, CIP Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes the Deputy City Manager to execute a contract and all necessary change orders with Tiseo Paving Company for the construction of Stacy Road Lanes 5 & 6 from Ridge Road to SH 121 and a right turn lane from SH 121 to Ridge Road for a total contract amount not to exceed $1,100,000.

 

BACKGROUND INFORMATION:

                     HW Lochner, Inc, prepared the construction plans for this project.

                     No right-of-way was acquired for this project as the two additional lanes on Stacy Road will be constructed in the existing median.

                     Three bids were received for this project on March 13, 2014.  The following is a summary of the bids:

 

Bid No.

Bidder

Bid Amount

1

Tiseo Paving Company

$  958,324.02

2

Pavecon Public Works, LP

$  1,025,044.20

3

XIT Paving and Construction, Inc

$  1,065,723.58

 

                     The bid from XIT Paving and Construction, Inc, did not include unit prices for each line item and was, therefore, considered non-responsive.

                     Tiseo Paving Company submitted the low bid in the amount of $958,324.02.

                     Tiseo Paving Company submitted references and qualifications that were verified in accordance with the bid specifications.

                     Tiseo Paving Company successfully completed the Alma Road and Silverado Trail project in 2013 and is currently working toward the successful completion of the FM 543 Connector Road project.

                     The contract documents require that this project be completed within 180 calendar days after issuance of the Notice to Proceed, which is expected in mid-April.  Construction is expected to be complete in October 2014.

 

FINANCIAL SUMMARY:

                     This Resolution authorizes a contract and all necessary change orders with Tiseo Paving Company for an amount not to exceed $1,100,000.

                     Funds are available in the Capital Improvements Program in ST3204.

 

BOARD OR COMMISSION RECOMMENDATION:                      N/A