File #: 17-315    Name: Hardin/McKinney Ranch Budget Amendment
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 3/21/2017 Final action:
Title: Consider/Discuss/Act on a Resolution Amending the Fiscal Year 2017 - 2021 Capital Improvements Program to Provide Funds for the Hardin Boulevard Lanes 5 & 6 Project (ST3211)
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Amending the Fiscal Year 2017 - 2021 Capital Improvements Program to Provide Funds for the Hardin Boulevard Lanes 5 & 6 Project (ST3211)

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic and Economic Growth 

 

MEETING DATE:                     March 21, 2017

 

DEPARTMENT:                      Development Services / Engineering

 

CONTACT:                       Gary Graham, PE, PTOE CIP and Transportation Engineering Manager

                     Jason Horn, PE, Civil Engineer

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of the Resolution.

 

ITEM SUMMARY: 

                     This Resolution amends expenditures in the Fiscal Year 2017 - 2021 Capital Improvement Program Project by transferring $600,000 from McKinney Ranch Parkway Improvements (ST1614) to Hardin Boulevard Lanes 5&6 (ST3211) for construction services.

 

BACKGROUND INFORMATION: 

                     Hardin Boulevard is the last roadway to be widened in a series of systematic north-south roadway improvements along the SH 121 corridor in order to increase mobility and drive economic growth.

                     Hardin Boulevard will be widened to provide a third through lane in each direction from McKinney Ranch Parkway to SH 121.  Additionally, southbound left turn lanes will be added at SH 121.

                     McKinney Independent School District is converting McKinney Ranch Parkway from a two lane roadway to a four lane divided roadway up to the eastern edge of their property line.

                     Three developments are also improving McKinney Ranch Parkway along their property lines.

                     This project is making the necessary improvements to McKinney Ranch Parkway in the areas between the developer built portions of roadway in order to have a completed four lane divided roadway from Hardin Boulevard to US 75.

                     The project will provide for mobility to the new MISD stadium as well as other development in the area.

 

FINANCIAL SUMMARY: 

                     The Amendment of the FY 2017 - 2021 Capital Improvements Program will deduct existing funding for the project ST1614 in the amount of $600,000 and add it to project ST3211 in the amount of $600,000.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A