File #: 12-103    Name: Alma Silverado Design Supplemental - KCI
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 2/21/2012 Final action: 2/21/2012
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement for Engineering Services Related to the Design of Alma Road from Stacy Road to Fire Station #8, and Silverado Trail from Alma Road to Comstock Elementary
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Supplemental Agreement for Engineering Services Related to the Design of Alma Road from Stacy Road to Fire Station #8, and Silverado Trail from Alma Road to Comstock Elementary

 

Summary

 

MEETING DATE:                      February 21, 2012

 

DEPARTMENT:                      Development Services / Engineering

 

CONTACT:                                           Carla Easton, PE, CIP Engineer

                                                               Matt Richardson, PE, CIP Program Manager

 

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of the Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes a contract amendment with Kennedy Consulting, Ltd. (KCI) to provide additional engineering services related to the Alma Road and Silverado Trail project, for a revised fee not to exceed $300,000. 

 

BACKGROUND INFORMATION:

                     An Engineering Services Agreement with KCI was authorized by City Council on June 7, 2011, for an amount not to exceed $250,000.  The contract amount was increased to $275,000 for additional services related to storm drain design on September 20, 2011. 

                     KCI has developed construction plans for the Alma Road and Silverado Trail project, in accordance with the design contract and current City design guidelines.  

                     The project is scheduled for completion prior to the opening of Comstock Elementary (FISD) in August.

                     The project schedule is contingent upon a clear ROW for construction operations and staff is currently negotiating the acquisition of right-of-way necessary for the project.  

                     The property at the southeast corner of Alma Road and Silverado Trail has a building with a conditioned space that has been finished out with a kitchen, restroom and office space for the operation of the business. 

                     This building will be impacted by the current design and will need to be removed and a new building will need to be constructed as a replacement building in order to complete the project as designed.

                     An alternative roadway layout has been developed that would allow the building to remain in its current location, as a temporary solution.

                     This roadway layout involves the construction of the two eastbound lanes in a temporary alignment, shifting them to the north and into the area where a raised median would typically have been constructed.  The westbound lanes are not affected by this shift.

                     This solution has the following advantages:

o                     The removal and reconstruction of the existing building would be a significant inconvenience to the property owner and upon completion the use of the buildings would be diminished by the reconfiguration.  With the alternate design this will not need to occur.

o                     The current use is not the highest and best use for this property and as development occurs in the future the buildings will be removed.

o                     The City will save the cost associated with the construction of a new building that would need to be removed when the property is developed.

o                     The temporary roadway alignment includes an offset that does not meet the criteria for permanent street design; however, the inconvenience to the motorist using the altered alignment will be tolerable during the interim period.

o                     As the tract develops the right-of-way required for the ultimate street alignment will be provided by the owner/developer of the tract through the platting process and the permanent eastbound lanes will be constructed by the developer in the alignment that conforms to the street design criteria.

o                     We have recently been informed of a property ownership dispute that further complicates the issue which would likely result in a significant delay to the removal and replacement of the building.

o                     This scenario is less expensive than the current plan that involves constructing a new building that will ultimately need to be removed.

                      To move forward with this solution, additional design services are needed to modify the construction plans and revise the acquisition documents. 

                     KCI has provided a proposal in the amount of $20,941.40 for these additional services.

 

FINANCIAL SUMMARY:

  • This Resolution authorizes a revised contract with KCI for an amount not to exceed $300,000.
  • Funding for this contract is included in the Capital Improvements Program ST9114.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A