File #: 16-020    Name: Public Safety Facility Phase 3 A/E Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 1/5/2016 Final action: 1/5/2016
Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Professional Services Contract with Brinkley, Sargent, Wiginton Architects of Dallas, Texas for Architectural and Engineering Services Related to the Design and Construction of Phase 3 of the Public Safety Facility
Attachments: 1. Resolution, 2. Proposed Contract

Title

Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Professional Services Contract with Brinkley, Sargent, Wiginton Architects of Dallas, Texas for Architectural and Engineering Services Related to the Design and Construction of Phase 3 of the Public Safety Facility

 

Summary

 

COUNCIL GOAL:                     Safe and Secure Community

 

MEETING DATE:                     January 5, 2016

 

DEPARTMENT:                      Public Works / Fire Department

 

CONTACT:                       Patricia L. Jackson, P.E., Facilities Construction Manager

                     Greg Conley, Chief of Police

                     Danny Kistner, Fire Chief

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of the Resolution.

 

ITEM SUMMARY: 

                     This Resolution authorizes a professional services contract to provide complete architectural and engineering services related to the master planning and design and construction of Phase 3 of the Public Safety Building located at 2200 Taylor-Burk Drive.

                     The selected consultant team, Brinkley, Sargent, Wiginton Architects (BSW), submitted a proposal to provide professional architectural and engineering services for the Phase 3 of the Public Safety Building for $679,125.

 

BACKGROUND INFORMATION: 

                     Nine firms submitted Statements of Qualifications on October 1, 2015 and were evaluated by members of the McKinney Police and Fire departments along with staff from the Development Services department.

                     From the nine firms that submitted, the four highest ranked architectural and engineering teams were interviewed.

                     After interviews, the firm of Brinkley, Sargent, Wiginton Architects was selected as the top ranking team.

                     Brinkley, Sargent, Wiginton Architects is an award winning professional architectural consulting services firm based in Dallas, Texas that specializes in public architecture.

                     Brinkley, Sargent, Wiginton Architects has performed successfully for the City of McKinney on several previous projects.

 

FINANCIAL SUMMARY: 

                     Public Safety Building Phase 3 (FC2229) was funded in the FY14-15 Capital Improvements Program with $7,350,000 of general obligation bonds from the 2006 and 2010 elections.

                     The Resolution authorizes a professional services contract for architectural and engineering services, including potential changes to the scope of services, with Brinkley, Sargent, Wiginton Architects for an amount not to exceed $735,000.

 

BOARD OR COMMISSION RECOMMENDATION: N/A