File #: 12-009PF    Name: The Salons of Volterra Addition Pre-Final
Type: Agenda Item Status: Consent Item
In control: Planning & Zoning Commission
On agenda: 2/14/2012 Final action:
Title: Consider/Discuss/Act on the Request by The Keller Salons of Volterra, on Behalf of Liberty Federal Savings Bank, for Approval of a Preliminary-Final for Lots 1 and 2, Block A of the Salons of Volterra Addition, Approximately 4.63 Acres, Located on the North Side of Virginia Parkway and Approximately 1,400 Feet East of Ridge Road.
Attachments: 1. PZ Staff Report, 2. Maps, 3. Letter of Intent, 4. Proposed Pre-final Plat, 5. Standard Conditions Checklist
Related files: 12-010SP, 12-007CP
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Consider/Discuss/Act on the Request by The Keller Salons of Volterra, on Behalf of Liberty Federal Savings Bank, for Approval of a Preliminary-Final for Lots 1 and 2, Block A of the Salons of Volterra Addition, Approximately 4.63 Acres, Located on the North Side of Virginia Parkway and Approximately 1,400 Feet East of Ridge Road.

 

Summary

 

MEETING DATE:                     February 14, 2012

 

DEPARTMENT:                      Development Services - Planning

 

CONTACT:                       Brandon Opiela, Senior Planner

                     Anthony Satarino, Planner

 

APPROVAL PROCESS:  The Planning and Zoning Commission is the final approval authority for the proposed preliminary-final plat.

 

 

STAFF RECOMMENDATION:  Staff recommends approval of the proposed preliminary-final plat with the following conditions:

 

1.                     The applicant satisfy the conditions as shown on the Standard Conditions for Preliminary-Final Plat Approval Checklist, attached.

 

Prior to filing the plat for record:

 

2.                     The applicant provide cross sections of the floodplain to verify the limits of the Erosion Hazard Setback Easements, subject to review and approval by the City Engineer.

 

3.                     The applicant verify that the 100-year fully developed floodplain is equivalent to the FEMA 100-year floodplain, subject to review and approval by the City Engineer.

 

4.                     The applicant revise the plat title block to provide the addition name prior to the lot number and block letter.

 

5.                     The applicant revise the plat to change the location of the drainage easement located near the southeastern property line in order to comply with the Tree Preservation Ordinance, subject to review and approval by the City Arborist.

 

 

 

APPLICATION SUBMITTAL DATE:         January 17, 2012 (Original Application)

                     January 30, 2012 (Revised Submittal)

                     February 2, 2012 (Revised Submittal)

                     February 6, 2012 (Revised Submittal)

                     February 9, 2012 (Revised Submittal)

                                                                                                                              

ITEM SUMMARY:  The applicant is proposing to subdivide approximately 4.63 acres into 2 lots, located on the north side of Virginia Parkway and approximately 1,400 feet east of Ridge Road.