File #: 10-510    Name: Mouzon Shade Structures
Type: Resolution Status: Approved and Finalized
In control: City Council Regular Meeting
On agenda: 11/2/2010 Final action: 11/2/2010
Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with SFCC, Inc. for the Construction of the Mouzon Baseball Spectator and Dugout Shade Structures Projects.
Attachments: 1. Resolution, 2. Bid Tabulation, 3. Norman Construction Letter, 4. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with SFCC, Inc. for the Construction of the Mouzon Baseball Spectator and Dugout Shade Structures Projects.

 

Summary

 

MEETING DATE:                     November 2, 2010

 

DEPARTMENT:                                           Parks, Recreation, and Open Space

 

CONTACT:                                            Lemuel Randolph, Director of Parks, Recreation and Open Space

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of the attached Resolution.

 

ITEM SUMMARY: 

                     The Mouzon Baseball Fields are located in Old Settler’s Park at 1307 Greenville Street.

 

                     Mouzon Baseball Spectator Shade Structures and Mouzon Baseball Dugout Shade Structures were bid together to create a larger project for a better construction market value.

 

                     SFCC, Inc. submitted the second lowest bid for the construction of Mouzon Ball Fields Spectator and Dugout Shade Structures projects with a bid of $308,600.

o                     A total of eight bids were submitted and accepted.

o                     Norman Construction was the lowest bidder, subsequently requesting to have their bid removed due to a $50,000 bust in their bid.

o                     A letter from Norman Construction requesting their bid to be pulled is included as an attachment.

 

BACKGROUND INFORMATION: 

                     LanArc Design, Inc., with Staff support, recommends accepting the bid from SFCC, Inc. for the construction of the Mouzon Baseball Spectator and Dugout Shade Structures projects.

 

                     This project is scheduled for completion in February 2011.

 

FINANCIAL SUMMARY: 

                     The Mouzon Baseball Spectator Shade Structures Project (PK0216) is a FY 10-11 Capital Improvements Program funded by MCDC funds.

 

§                     Architectural and Engineering Design Fees                              $  23,900

§                     Construction Contract                                                                                          $217,200   

§                     Project contingency                                                                                                            $148,900

                     Potential source of transfer to PK0217

                     Potential source of transfer to PK6045

       Total                                                                                                                                                      $390,000

 

                     The Mouzon Baseball Dugout Shade Structures Project (PK0217) is a FY10-11 Capital Improvements Program funded by MCDC funds.

o                     The total project budget including design and construction of the improvements is currently $75,000. A fund transfer is needed to complete the project as planned.

 

o                     Below is a breakdown showing what the new project budget would be if the fund transfer of $20,400 is approved.

§                     Architectural and Engineering Design Fees                              $   4,000

§                     Construction Contract                                                                                          $ 91,400   

§                     Additional funding needed                                                                                       $(20,400)

       Total                                                                                                                                                      $ 95,400

 

                     In a concurrent CIP Amendment, Staff is requesting fund transfers in the amount of $20,400 to be appropriated from Mouzon Baseball Spectator Shade Structures project (PK0216) to Mouzon Baseball Dugout Shade Structures project (PK0217).

 

BOARD OR COMMISSION RECOMMENDATION:

                     On October 14, 2010, the Parks, Recreation and Open Space Advisory Board recommended approval of the construction contract for the Mouzon Ball Fields Spectator and Dugout Shade Structures projects.