File #: 12-339    Name: US 75 South BGE Supplemental Agreement
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 5/15/2012 Final action: 5/15/2012
Title: Consider/Discuss/Act on a Resolution Authorizing a Supplemental Agreement with Brown & Gay Engineers, Inc, for Additional Engineering Design Services Required for the US 75 Utility Relocation Project from SH 121 to White Avenue
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Authorizing a Supplemental Agreement with Brown & Gay Engineers, Inc, for Additional Engineering Design Services Required for the US 75 Utility Relocation Project from SH 121 to White Avenue

 

Summary

 

MEETING DATE:                     May 15, 2012

 

DEPARTMENT:                     Development Services/Engineering

 

CONTACT:                     Danny Still, PE, CIP Engineer

                     Paul Tucker, PE, Senior Utility Engineer

 

 

RECOMMENDED CITY COUNCIL ACTION:

                     Approval of Resolution.

 

ITEM SUMMARY:

                     This Resolution authorizes the City Manager to execute a supplemental agreement with Brown & Gay Engineers, Inc, for additional engineering design services required for the US 75 Utility Relocation Project from SH 121 to White Avenue, for a revised total fee not to exceed $815,000.

 

BACKGROUND INFORMATION:

                     A professional services contract with Brown and Gay Engineers was authorized by City Council on June 1, 2010 for the design of the US 75 Utility Relocation Project from SH 121 to White Avenue, for an amount not to exceed $706,000.

                     During the course of design and construction of this project the following issues were encountered that require additional design work.

-                     Additional design services were needed to account for unforeseen field conditions and corrections to right-of-way information provided by TxDOT.

-                     Design changes needed to avoid the acquisition of a potentially costly easement at the northeast corner of US 75 and Greenwood Road.  At this location, the initial plans called for an existing sewer main to be relocated into an easement across the frontage of that property.  After easement negotiation was initiated the acquisition team recognized the acquisition cost would likely be very high.  At that point alternative design options were developed and because the right-of-way did not have any franchise utility conflicts, an alternative route for the sewer main was found on the right-of-way eliminating the need for the easement.

-                     Additional design services for a new 16-inch water main along the northbound frontage road.  This water main begins at an existing water main at Marketplace Drive, crosses the frontage of the proposed Emerson site, and connects to an existing water main at Gateway Boulevard.

                     Brown and Gay Engineers has submitted a proposal for the required additional design services in the amount of $96,095, which increases the total fee from $705,645 to $801,740.

 

FINANCIAL SUMMARY:

                     This Resolution authorizes a supplemental agreement with Brown & Gay Engineers, Inc, for a total contract amount not to exceed $815,000.

                     Current funding for this project is included in the Capital Improvements Program WA9118 ($530,000) and WW9119 ($285,000).

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A