Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Johnson, Mirmiran & Thompson, Inc. for Professional Engineering Design Services for the Intersection Capacity Improvements at US Highway 380 and Community Avenue Project and Authorizing Any Necessary Supplemental Agreements
Summary
COUNCIL GOAL: Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)
MEETING DATE: March 01, 2022
DEPARTMENT: Development Services / Engineering
CONTACT: Nick Ataie, PE, Engineering CIP Manager
Aniswarie Kanamazina, PE, CIP Engineer
RECOMMENDED CITY COUNCIL ACTION:
• Approval of Resolution.
ITEM SUMMARY:
• This Resolution authorizes the City Manager to execute a contract in the amount of $374,966 as well as all required supplemental agreements thereto, with Johnson, Mirmiran & Thompson, Inc. for professional consulting engineering services for the Intersection Capacity Improvements at US Highway 380 and Community Avenue Project (ST2011), for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $430,000.
BACKGROUND INFORMATION:
• The City of McKinney Engineering Department has identified a need for intersection capacity improvements at US 380 and Community Avenue including the addition of additional turn lanes and traffic flow improvements.
• These intersection capacity improvements have been included in the FY22 Capital Improvement Plan budget for CIP Project ST2011 including:
o $800,000 in collected roadway impact fees eligible for use in improving intersection capacity.
o $1,200,000 in grant funding approved under the NCTCOG Congestion Mitigation and Air Quality Improvement Program (CMAQ).
• The scope of improvements under this project include:
o Conversion of a single westbound left-turn lane on US 380 to dual left-turn lanes.
o Conversion of a single eastbound left-turn lane on US 380 to dual left-turn lanes.
o Construction of a westbound right-turn lane on US 380.
o Reconstruction of the eastbound right-turn lane on US 380.
o Conversion of a single southbound left-turn lane on Community Avenue to dual left-turn lanes.
o Associated paving, drainage, grading, lighting, and sign/marking modifications at the intersection to accommodate the improvements.
• Due to the grant funding associated with this project and the improvements being primarily located on a TxDOT roadway, additional design phase services will be required including meeting TxDOT design specifications, conducting environmental approvals, public involvement, and meeting special bidding and construction permitting requirements.
• Johnson, Mirmiran & Thompson, Inc. submitted a response to RFQ 21-41 for On-Call Roadway Design Services. They were one of eleven firms shortlisted by City Council on September 7, 2021.
• Johnson, Mirmiran & Thompson, Inc. submitted a proposal for this project in the amount of $374,966.
• The preliminary opinion of probable construction cost is $1,348,463.
• The fee for basic services is $204,130 (15.14% of the engineer’s opinion of probable cost of construction) and the fee for special services is $170,836 (12.67% of the engineer’s opinion of probable cost of construction).
• Design of this project is anticipated to take approximately 1 year to complete with construction estimated to begin in March 2023.
FINANCIAL SUMMARY:
• This Resolution authorizes a design contract and any necessary supplemental agreements with Johnson, Mirmiran & Thompson, Inc. for an amount not to exceed $430,000.
• Funds are available in the Capital Improvements Program Project ST2011.
• One hundred percent (100%) local funds will be utilized for professional engineering design services.
• Grant funding through the NCTCOG has been previously executed under an Advance Funding Agreement (AFA) between the City and TxDOT who will administer those funds.
• With the approval of this item, $1,570,000 will remain in ST2011.