File #: 21-0648    Name: FC2058 - Crossland - GMP Amendment
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 7/20/2021 Final action: 7/20/2021
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Contract with Crossland Construction Company, Inc. (Crossland) whose local office is in Prosper, Texas for a Guaranteed Maximum Price (GMP) Related to the Construction Remodel of the North Public Works Complex Project (FC2058) Located at 3501 North Central Expressway, McKinney
Attachments: 1. Resolution, 2. GMP Proposal, 3. Value Management Log

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract Amendment to the Construction Manager at Risk (CMAR) Contract with Crossland Construction Company, Inc. (Crossland) whose local office is in Prosper, Texas for a Guaranteed Maximum Price (GMP) Related to the Construction Remodel of the North Public Works Complex Project (FC2058) Located at 3501 North Central Expressway, McKinney

 

Summary

 

COUNCIL GOAL:                     Operational Excellence

                     (2B: Balance Available Resources to Accommodate the Growth

                     and Maintenance Needs of the City)

 

MEETING DATE:                     July 20, 2021

 

DEPARTMENT:                      Public Works

 

CONTACT:                     Patricia L. Jackson, PE, Facilities Construction Manager

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of the Resolution.

 

ITEM SUMMARY: 

                     This Resolution establishes a Guaranteed Maximum Price (GMP) of $8,749,801 as proposed by Crossland Construction Company, Inc. 

                     This Resolution authorizes the City Manager to execute a contract amendment with Crossland Construction Company, Inc., the Construction Manager at Risk for the North Public Works Complex Project.

 

BACKGROUND INFORMATION: 

                     The construction documents were issued on April 30, 2021 and have been advertised for bids by Crossland Construction Company, Inc.

                     Crossland has compiled the bids and submitted a final Guaranteed Maximum Price for approval.

                     With this approval, Crossland will be notified to begin construction with completion scheduled for June 2022.

                     Crossland Construction Company, Inc. is ranked among the top general contractors in North Texas and the nation. They are a Prosper, Texas based firm and have successfully completed multiple projects for McKinney and many other municipalities.

 

FINANCIAL SUMMARY: 

                     The Resolution authorizes the City Manager to execute a contract amendment to the existing Construction Manager at Risk (CMAR) services contract, for construction services with Crossland Construction Company, Inc. for an amount not to exceed $8,749,801.

                     A companion budget amendment being presented will amend the Fiscal Year 2020-2021 Annual Budget and the 2021-2025 Capital Improvement Program to provide $1,250,000 additional funding for the North Public Works Complex Project (FC2058).

                     With approval of this item and the companion agenda item, the total project budget remaining in project FC2058 will be $515,646.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A