File #: 13-161    Name: Gabe Softball Sanitary Sewer
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 2/19/2013 Final action: 2/19/2013
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with North Texas Contracting for the Construction of the Gabe Nesbitt Softball Sanitary Sewer Replacement Project.
Attachments: 1. Agenda Item Summary, 2. Resolution, 3. Location Map, 4. Bid Tabulation
 
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with North Texas Contracting for the Construction of the Gabe Nesbitt Softball Sanitary Sewer Replacement Project.
 
Summary
 
MEETING DATE:      February 19, 2013
 
DEPARTMENT:       Parks, Recreation, and Open Space
 
CONTACT:        Lemuel Randolph, Director of Parks, Recreation and Open Space
 
RECOMMENDED CITY COUNCIL ACTION:      
·      Approval of the attached Resolution.
 
ITEM SUMMARY:  
·      The Gabe Nesbitt Community Park five-field complex was completed in May of 2005 before downstream sanitary sewer was available.  Sanitary sewer effluent has been pumped under pressure to the baseball three field complex where it gravity flows to the east.
 
·      The pump has been an increasingly labor intensive maintenance problem.  
 
·      This project will entail removing the sanitary sewer pump and installing sanitary sewer lines to an existing manhole located near the newly constructed tennis courts.
 
·      The North Texas Contracting bid of $130,185 was the low bidder and was very close to the construction cost estimate of $130,000.  
 
·      A total of 2 bids were submitted, one being disqualified as non-responsive.
 
BACKGROUND INFORMATION:  
·      Staff recommends accepting the bid from North Texas Contracting for the construction of the Gabe Nesbitt Softball Sanitary Sewer Replacement project.
 
·      North Texas Contracting is currently under contract with the City for utility projects.
 
·      This project was designed in-house by the City's Engineering Department.
 
·      This project is scheduled for completion in May 2013.
 
FINANCIAL SUMMARY:  
·      Gabe Nesbitt Softball Sanitary Sewer Replacement Project (PK2259) is a FY 12-13 Capital Improvements Program project funded by MCDC funds.
 
·      The total project budget is $200,000.
·      Project designed by Engineering Staff                           $           0
·      Construction Contract                                             $ 150,185
·      Topographic Survey                                 $     4,200
·      Funding in excess of Project Encumbrances             $   45,615     
   Total                                                                                $ 200,000
 
BOARD OR COMMISSION RECOMMENDATION:
·      On February 14, 2013, the Parks, Recreation and Open Space Advisory Board recommended approval of the construction contract for the Gabe Nesbitt Softball Sanitary Sewer Replacement Project.