Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Jim Bowman Construction Company, LP, for Construction of Jefferson Street, from Rockwall to Healy, and Lindsey Street from Elm to Rockwall
Summary
MEETING DATE: June 21, 2011
DEPARTMENT: Development Services/Engineering
CONTACT: Carla Easton, PE, CIP Engineer
Jack Carr, PE, Director of Engineering
RECOMMENDED CITY COUNCIL ACTION: Approval of Resolution.
ITEM SUMMARY:
• This Resolution authorizes a contract with Jim Bowman Construction Company, LP, for the construction of Jefferson Street, from Rockwall to Healy, and Lindsey Street, from Elm to Rockwall, for an amount not to exceed $1,900,000.
BACKGROUND INFORMATION:
• HDR Engineering, Inc. prepared the construction plans for this project.
• On June 2, 2011, four bids were received for this project and Jim Bowman Construction Company, LP, submitted the low bid in the amount of $1,722,292.69.
• References for Jim Bowman Construction Company, LP, were verified in accordance with the contract documents.
• The contract documents require this project to be completed within 360 calendar days after issuance of the notice to proceed.
• A summary of the four bids received for this project are as follows:
|
Bidder |
Bid Amount |
|
Jim Bowman Construction Company, LP |
$1,722,292.69 |
|
Tiseo Paving Company |
$1,743,711.10 |
|
RKM Utility |
$1,869,548.80 |
|
McMahon Contracting, LP |
$1,893,361.68 |
FINANCIAL SUMMARY:
• This Resolution authorizes a contract with Jim Bowman Construction Company, LP, for an amount not to exceed $1,900,000.
• Funds are available in the Capital Improvements Program in CO2127 ($1,550,500 GO Bonds) and ($349,500 Revenue Bonds).
BOARD OR COMMISSION RECOMMENDATION:
• N/A