Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with Mario Sinacola and Sons Excavating, Inc., for the Construction of the Wilmeth Road (Lake Forest Drive to Hardin Boulevard) Project
Summary
COUNCIL GOAL: Direction for Strategic & Economic Growth
(1A: Establish regional and infrastructure incentives to increase economic growth)
MEETING DATE: January 4, 2022
DEPARTMENT: Development Services / Engineering
CONTACT: Nick Ataie, PE, Engineering CIP Manager
Blake Sills, PE, CIP Engineer II
RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with Mario Sinacola and Sons Excavating, Inc., for the Construction of the Wilmeth Road (Lake Forest Drive to Hardin Boulevard) Project (ST1719) for a total contract amount not to exceed $21,000,000.
BACKGROUND INFORMATION:
* Kimley-Horn and Associates, Inc. prepared the construction plans for the Wilmeth Road (Lake Forest Drive to Hardin Boulevard) Project (ST1719).
* Wilmeth Road is currently identified as a four-lane divided greenway arterial (G4D Classification) per the Master Thoroughfare Plan.
* This project will construct a new segment of Wilmeth Road as a 4-lane divided roadway (approximately 1.7 miles in length) from Lake Forest Drive to Hardin Boulevard.
* Construction of this new segment of Wilmeth Road will support further development of City's Northwest Sector and improve mobility by further reducing reliance on US 380 for east/west connectivity to/from US 75.
* The project will also include construction of the southbound lanes of Hardin Boulevard from the existing terminus south of Holley Ridge Way to Wilmeth Road (approximately 1,550 linear feet) and the northbound lanes of Taylor Burke Drive from Ryeland Cove to Wilmeth Road (approximately 1,100 linear feet).
* Multi-lane roundabouts will be constructed at ...
Click here for full text