File #: 21-1171    Name: GR2109 - BA - Ordinance - Silos Project
Type: Ordinance Status: Consent Item
In control: City Council Regular Meeting
On agenda: 1/4/2022 Final action:
Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2021-2022 Annual Budget to Provide Funds for the Purpose of Gap Funding the McKinney Silos Art Mural Project (GR2109)
Attachments: 1. Ordinance

Title

Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2021-2022 Annual Budget to Provide Funds for the Purpose of Gap Funding the McKinney Silos Art Mural Project (GR2109)

Summary

COUNCIL GOAL:                     Quality of Life

MEETING DATE:                     January 4, 2022

DEPARTMENT:                      MPAC / Main Street

CONTACT:                       Amy Rosenthal, Program Director

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of ordinance to amend the FY2022 budget

ITEM SUMMARY: 

                     This Ordinance amends expenditures in the FY2021-2022 Annual Budget by transferring $398,000 from Hotel/Motel Fund Balance and appropriating in the Public Art Fund for the McKinney Silos Art Mural Project (GR2109) to serve as project gap funding.

                     This Ordinance also amends expenditures in the FY2021-2022 Annual Budget by appropriating $90,000 of TCA grant funds in the Public Art Fund for the McKinney Silos Art Mural Project (GR2109)

                     This project is eligible for the use of Hotel/Motel taxes.

                     HOT taxes will only serve as gap funding between grants and donations secured for the project and the actual project costs.

BACKGROUND INFORMATION: 

                     In June 2021 Council authorized a transfer of $380,000 from the Hotel/Motel Tax Fund to serve as gap funding for the initial sitework and artist agreement. 

                     There is a companion agenda item on this meeting for Western Specialty Contractors for Design / Build (D/B) Services Related to the Phase 1 Construction Services and Engineering of the McKinney Silos Restoration Project (GR2109)

FINANCIAL SUMMARY: 

                     This ordinance amends the FY2021-2022 annual budget by appropriating $488,000 in the Public Art Fund for the McKinney Silos Art Mural Project.

                     The total estimated McKinney Silos Art Mural project budget is $868,000:

                     The City will be responsible for future maintenance cost of the mural and silos.

BOARD OR COMMISSION RECOMMENDATION:

                     McKinney Main Street and McKinney Arts Commission have both provided support for this project.