File #: 21-0338    Name: Erosion Mitigation - Airport Runway Safety
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 4/20/2021 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Agreement with the Texas Department of Transportation (TxDOT) and Required Local Match Funds for the Stormwater Erosion Mitigation Phase 2 (Improve Runway Safety Area Drainage for RW 18-36) Project; and Providing an Effective Date
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Agreement with the Texas Department of Transportation (TxDOT) and Required Local Match Funds for the Stormwater Erosion Mitigation Phase 2 (Improve Runway Safety Area Drainage for RW 18-36) Project; and Providing an Effective Date

 

Summary

 

COUNCIL GOAL:                     Maximize the Development Potential of McKinney National Airport

                     

                     3B: Identify and implement land use regulations and policies with preserve and expand long-term operational excellence

 

MEETING DATE:                     April 20, 2021

 

DEPARTMENT:                      Airport

 

CONTACT:                       Ken Carley, Airport Director

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approve the Resolution

 

ITEM SUMMARY: 

                     Grading improvements and drainage enhancements are necessary to mitigate erosion in the runway safety area. Total project costs are estimated to be $1,975,000.

 

BACKGROUND INFORMATION: 

                     TxDOT will administer the project and has programmed $650,000 in grant funding in its Aviation Capital Improvement Program.                                          

 

FINANCIAL SUMMARY: 

                     The City will be responsible for project costs estimated to be $1,325,000.

                     There is an accompanying ordinance to reappropriate Airport Construction Fund Balance to CIP project AI2116 Stormwater Erosion Mitigation Phase 2 to cover the City match.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A