File #: 17-1260    Name: Redbud Transmission Line - Collin College Interlocal Agreement
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 12/19/2017 Final action: 12/19/2017
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into an Interlocal Agreement with Collin County Community College District for the Construction and Reimbursement of Costs Related to Construction Activities of the Water Line Installation along the Public Safety Training Facility Site, Generally Located on the East Side of Redbud Boulevard and Approximately 800 Feet South of Bloomdale Road
Attachments: 1. Resolution, 2. Interlocal Agreement, 3. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Enter into an Interlocal Agreement with Collin County Community College District for the Construction and Reimbursement of Costs Related to Construction Activities of the Water Line Installation along the Public Safety Training Facility Site, Generally Located on the East Side of Redbud Boulevard and Approximately 800 Feet South of Bloomdale Road

Summary

COUNCIL GOAL: Direction for Strategic and Economic Growth

MEETING DATE: December 19, 2017

DEPARTMENT: Development Services

CONTACT: Nick Ataie, PE, Engineering CIP Manager
Blake Sills, PE, CIP Engineer

RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution

ITEM SUMMARY:
* This item authorizes the City Manager to enter into an Interlocal Agreement with the Collin County Community College District (College) for the construction and reimbursement of construction activities related to the City's Redbud Pump Station 794 PP Transmission Water Line Project (WA1624) and the Public Safety Training Facility (PSTF).
* The proposed agreement states that the City may install the transmission line across the Water Line Easement area located on the PSTF site. The City will reimburse the College for an amount equal to $24,000, which includes remobilization costs of the College's contractor, and costs associated with the construction and removal of a temporary flex base driveway that will provide temporary access to Redbud Boulevard across the Water Line Easement area.
* The City is currently under contract with S.J. Louis Construction of Texas, Ltd. for the construction of the water transmission line (WA1624).

BACKGROUND INFORMATION:
* The construction contract for the Redbud Pump Station 794 PP Transmission Water Line Project (WA1624) was approved by Resolution No. 2017-09-179 (R) on September 19, 2017.
* The Redbud Pump Station 794 PP Transmission Water Line Project (WA1624) is currently under construction. The water line is e...

Click here for full text