File #: 12-128    Name: Skatepark change order
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 3/6/2012 Final action: 3/6/2012
Title: Consider/Discuss/Act on a Resolution Authorizing a Change Order to the Design/Build Contract for the Skatepark at Gabe Nesbitt Community Park.
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Authorizing a Change Order to the Design/Build Contract for the Skatepark at Gabe Nesbitt Community Park.

 

Summary

 

MEETING DATE:                     March 6, 2012

 

DEPARTMENT:                      Parks, Recreation, and Open Space

 

CONTACT:                       Lemuel Randolph, Director of Parks, Recreation and Open Space

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     This Resolution authorizes a change order of $60,000 to the $1,900,000 design/build contract with Dean Construction Inc. for an amount not to exceed $1,900,000.

 

ITEM SUMMARY: 

                     An additional $60,000 of design funding is required to relocate the skatepark within the Gabe Nesbitt Community Park.

                     The Guaranteed Maximum Price will remain at $1,900,000. The change order of $60,000 will reduce the construction budget from $1,667,000 to $1,607,000.

 

 

BACKGROUND INFORMATION: 

                     A contract was awarded to Dean Construction Inc for $1,900,000 in January 2010 to provide design/build services related to the design and construction of the McKinney Skatepark located in Gabe Nesbitt Community Park.

 

FINANCIAL SUMMARY: 

                     Current funding for this contract is available in the Capital Improvements Program, project PK1214.

                     This Resolution authorizes a change order of $60,000 to be deducted from construction funds and placed in design funds.

                     

BOARD OR COMMISSION RECOMMENDATION:

                     NA