Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Teague, Nall, and Perkins, Inc. for Professional Engineering Design Services for the Bloomdale Rd and FM 543 Realignment Project and Any Necessary Supplemental Agreements
Summary
COUNCIL GOAL: Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)
MEETING DATE: January 18, 2022
DEPARTMENT: Development Services / Engineering
CONTACT: Nick Ataie, PE, CIP Engineering Manager
Jason Horn, PE, CIP Project Manager
RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract in the amount of $148,900, as well as all required supplemental agreements thereto, with Teague, Nall, and Perkins, Inc. for professional consulting engineering services for the Bloomdale Rd and FM 543 Realignment Project (CIP Project ST4229), for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $175,000.
BACKGROUND INFORMATION:
* Bloomdale Rd is currently a two-lane undivided arterial from Redbud Blvd to State Highway 5 and is currently identified as a six-lane principal arterial (P6D) in the adopted Master Thoroughfare Plan.
* The FY22-26 Capital Improvement Program (CIP) includes funding for the expansion of Bloomdale Road from 2-lanes to a 4-lane divided throughfare including establishment of a new intersection of former FM 543 (currently identified as Spur 195) to allow Bloomdale Road to have a more direct connection to State Highway 5.
* In addition, the Engineering Department has previously conducted a high-level traffic study which has identified the Bloomdale Rd and Spur 195 intersection as a potential candidate for a multi-lane roundabout.
* The initial professional services contract included in this agenda item will include a detailed traffic study and roadway alignment determination prior...