File #: 13-1018    Name: Custer South Illumination
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 10/1/2013 Final action: 10/1/2013
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Roadway Solutions, Inc., for the Construction of the Custer Road Illumination from Stonebridge Drive to US 380 Project and Authorizing All Required Change Orders
Attachments: 1. Resolution, 2. Location Map, 3. Bid Award Recommendation Letter
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Roadway Solutions, Inc., for the Construction of the Custer Road Illumination from Stonebridge Drive to US 380 Project and Authorizing All Required Change Orders

Summary

MEETING DATE: October 1, 2013

DEPARTMENT: Development Services / Engineering

CONTACT: Gary Graham, PE, PTOE, Transportation Engineering Manager
Danny Still, PE, CIP Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract with Roadway Solutions, Inc., for the construction of the Custer Road Illumination from Stonebridge Drive to US 380 Project and authorizing all required change orders for a total contract amount not to exceed $525,000.

BACKGROUND INFORMATION:
* Savant Group, Inc, prepared the construction plans for this project.
* Five bids for this project were received on September 12, 2013. The following is a summary of the bids:

Bid No.
Bidder
Bid Amount|1313|Roadway Solutions, Inc.
$ 454,960.00|1313|Highway ITS
$ 479,429.94|1313|Groves Electrical Service, Inc.
$ 510,989.00|1313|Mel's Electric, LP
$ 535,693.75|1313|Analytical Technology Consultants, Inc.
$ 601,561.80

* Roadway Solutions, Inc., submitted the low bid in the amount of $454,960.
* Roadway Solutions, Inc., submitted references and qualifications that were verified in accordance with the bid specifications.
* Roadway Solutions, Inc., has successfully completed projects for the City of McKinney in the recent past.
* The contract documents require that this project be completed within 150 calendar days after issuance of the Notice to Proceed.

FINANCIAL SUMMARY:
* This Resolution authorizes a contract and all required change orders with Roadway Solutions, Inc., for an amount not to exceed $525,000.
* Funds are available in the Capital Improvements Program in ST2056.

BOARD OR COMMISSION R...

Click here for full text