File #: 11-423    Name: MPAC Building Improvements Funding
Type: Agenda Item Status: Public Hearing
In control: City Council Regular Meeting
On agenda: 9/6/2011 Final action: 9/6/2011
Title: Conduct a Public Hearing to Consider/Discuss/Act on Application #11-06 as Submitted by City of McKinney Public Works Department Requesting up to $260,000 for Building Improvement to McKinney Performing Arts Center
Attachments: 1. Application, 2. 072811 Draft Minutes

 Title

Conduct a Public Hearing to Consider/Discuss/Act on Application #11-06 as Submitted by City of McKinney Public Works Department Requesting up to $260,000 for Building Improvement to McKinney Performing Arts Center

Summary

 

MEETING DATE:                     September 6, 2011

 

DEPARTMENT:                      McKinney Community Development Corporation

 

CONTACT:                                            Cindy Schneible, Executive Director

                                                                                    

RECOMMENDED CITY COUNCIL ACTION:                     

                     The board of directors of the McKinney Community Development Corporation recommends approval of this grant

 

ITEM SUMMARY: 

                     Replace exterior wood doors and hardware with energy efficient metal aluminum or fiberglass doors.

 

                     Install new cooling roof top unit, and adding return air flow in rear of Courtroom Theater. 

 

                     Install magnetic fiberglass panels over single pane glass windows for higher energy efficiency and to reduce exterior noise. 

 

                     Install sound absorbing panels above wainscoting on the first floor and in the hallways on all levels.

 

                     Install larger French drain on west side of building to eliminate water intrusion

 

                     Install a visual art and light tracking system to display public art

 

                     Power clean exterior brick and cast concrete to remove dirt and mold

 

                     Marble polishing and floor cleaning

 

                     Paint interior walls and wood stain selected areas

 

                     Sand, Stain and seal wood floors throughout facility

 

BACKGROUND INFORMATION: 

                     MCDC attorney has confirmed eligibility for 4B funding