File #: 14-329    Name: Stacy 5 & 6 - Construction
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 4/1/2014 Final action: 4/1/2014
Title: Consider/Discuss/Act on a Resolution Authorizing the Deputy City Manager to Execute a Contract and All Necessary Change Orders with Tiseo Paving Company for the Construction of Stacy Road Lanes 5 & 6 from Ridge Road to SH 121 and a Right Turn Lane from SH 121 to Ridge Road
Attachments: 1. Resolution, 2. Award Recommendation Letter, 3. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the Deputy City Manager to Execute a Contract and All Necessary Change Orders with Tiseo Paving Company for the Construction of Stacy Road Lanes 5 & 6 from Ridge Road to SH 121 and a Right Turn Lane from SH 121 to Ridge Road

Summary

MEETING DATE: April 1, 2014

DEPARTMENT: Development Services / Engineering

CONTACT: Gary Graham, PE, CIP Manager
Danny Still, PE, CIP Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the Deputy City Manager to execute a contract and all necessary change orders with Tiseo Paving Company for the construction of Stacy Road Lanes 5 & 6 from Ridge Road to SH 121 and a right turn lane from SH 121 to Ridge Road for a total contract amount not to exceed $1,100,000.

BACKGROUND INFORMATION:
* HW Lochner, Inc, prepared the construction plans for this project.
* No right-of-way was acquired for this project as the two additional lanes on Stacy Road will be constructed in the existing median.
* Three bids were received for this project on March 13, 2014. The following is a summary of the bids:

Bid No.
Bidder
Bid Amount|1313|Tiseo Paving Company
$ 958,324.02|1313|Pavecon Public Works, LP
$ 1,025,044.20|1313|XIT Paving and Construction, Inc
$ 1,065,723.58

* The bid from XIT Paving and Construction, Inc, did not include unit prices for each line item and was, therefore, considered non-responsive.
* Tiseo Paving Company submitted the low bid in the amount of $958,324.02.
* Tiseo Paving Company submitted references and qualifications that were verified in accordance with the bid specifications.
* Tiseo Paving Company successfully completed the Alma Road and Silverado Trail project in 2013 and is currently working toward the successful completion of the FM 543 Connector Road project.
* The contract documents require that this project be completed within 180 calendar days after issuance of th...