Title
Conduct a Public Hearing to Consider/Discuss/Act on the Request by Cross Engineering Consultants, Inc., on Behalf of DFA, Ltd., for Approval of a Site Plan for the Oak Hollow Office Warehouse Park, Being Fewer than 4 Acres, Located Approximately 300 Feet South of Wilmeth Road and on the West Side of State Highway 5 (McDonald Street)
Summary
MEETING DATE: March 26, 2013
DEPARTMENT: Planning
CONTACT: Brandon Opiela, Planning Manager
APPROVAL PROCESS: The Planning and Zoning Commission is the final approval authority for the proposed site plan.
STAFF RECOMMENDATION: Staff recommends approval of the proposed site plan with the following conditions:
1. The applicant satisfy the conditions as shown on the Standard Conditions for Site Plan Approval Checklist, attached.
2. The applicant receive approval of a variance to utilize the existing tree line along the northern property line to screen the proposed office/warehouse use from the adjacent residential use.
3. The applicant receive approval of a variance to utilize a living screen to screen the bay doors from the adjacent non-residential use along the southern property line.
APPLICATION SUBMITTAL DATE: July 30, 2012 (Original Application)
August 14, 2012 (Revised Submittal)
August 22, 2012 (Revised Submittal)
January 30, 2013 (Revised Submittal)
February 18, 2013 (Revised Submittal)
February 27, 2013 (Revised Submittal)
March 4, 2013 (Revised Submittal)
March 6, 2013 (Revised Submittal)
ITEM SUMMARY: The applicant is proposing to construct a total of five (5) office/warehouse buildings (totaling 19,320 square feet) in two phases, on approximately 3.20 acres, located approximately 300 feet south of Wilmeth Road and on the west side of State Highway 5 (McDonald Street).