Title
Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Professional Services Contract with Brinkley, Sargent, Wiginton Architects of Dallas, Texas for Architectural and Engineering Services Related to the Design and Construction of Phase 3 of the Public Safety Facility
Summary
COUNCIL GOAL: Safe and Secure Community
MEETING DATE: January 5, 2016
DEPARTMENT: Public Works / Fire Department
CONTACT: Patricia L. Jackson, P.E., Facilities Construction Manager
Greg Conley, Chief of Police
Danny Kistner, Fire Chief
RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution.
ITEM SUMMARY:
* This Resolution authorizes a professional services contract to provide complete architectural and engineering services related to the master planning and design and construction of Phase 3 of the Public Safety Building located at 2200 Taylor-Burk Drive.
* The selected consultant team, Brinkley, Sargent, Wiginton Architects (BSW), submitted a proposal to provide professional architectural and engineering services for the Phase 3 of the Public Safety Building for $679,125.
BACKGROUND INFORMATION:
* Nine firms submitted Statements of Qualifications on October 1, 2015 and were evaluated by members of the McKinney Police and Fire departments along with staff from the Development Services department.
* From the nine firms that submitted, the four highest ranked architectural and engineering teams were interviewed.
* After interviews, the firm of Brinkley, Sargent, Wiginton Architects was selected as the top ranking team.
* Brinkley, Sargent, Wiginton Architects is an award winning professional architectural consulting services firm based in Dallas, Texas that specializes in public architecture.
* Brinkley, Sargent, Wiginton Architects has performed successfully for the City of McKinney on several previous projects.
FINANCIAL SUMMARY:
* Public Safety Building Phase 3 (FC2229) was funded in the FY...
Click here for full text