File #: 13-555    Name: US 75 Corridor Study
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 6/4/2013 Final action: 6/4/2013
Title: Consider/Discuss/Act on Resolution Supporting a Corridor Study for US 75 from IH 635 to SH 121 (Sam Rayburn Tollway) in Dallas and Collin Counties to Identify Alternatives and Solutions to Address Mobility Needs in the Corridor and to Minimize Impacts in the Study Area and Requesting that the Texas Department of Transportation Extend the Limits of the Corridor Study to Telephone Road
Attachments: 1. Agenda Item Summary, 2. Resolution
Title
Consider/Discuss/Act on Resolution Supporting a Corridor Study for US 75 from IH 635 to SH 121 (Sam Rayburn Tollway) in Dallas and Collin Counties to Identify Alternatives and Solutions to Address Mobility Needs in the Corridor and to Minimize Impacts in the Study Area and Requesting that the Texas Department of Transportation Extend the Limits of the Corridor Study to Telephone Road

Summary

MEETING DATE: June 4, 2013

DEPARTMENT: Development Services/Engineering

CONTACT: Gary Graham, PE, PTOE, Transportation Engineering Manager


RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution.

ITEM SUMMARY:
* This Resolution supports a corridor study for the section of US 75 from IH 635 to SH 121 (Sam Rayburn Tollway) Dallas and Collin Counties to identify alternatives and solutions to address mobility needs in the corridor and to minimize impacts in the study area.
* This Resolution also requests that the Texas Department of Transportation (TxDOT) extend the limits of the corridor study to Telephone Road.

BACKGROUND INFORMATION:
* TxDOT began work on a corridor study for US 75 between IH 635 and SH 121 (Sam Rayburn Tollway) in late 2012. This study will look at long-term mobility needs in the US 75 corridor and will identify alternatives to address these needs.
* TxDOT has been collaborating with the various local jurisdictions impacted by this project, including the cities of Dallas, Richardson, Plano, Allen, Fairview, and McKinney, Dallas County, Collin County, Dallas Area Rapid Transit, and the North Central Texas Council of Governments.
* Traffic volumes are anticipated to increase significantly over the next 20 years:
Location
2011 Volume
2035 Demand
(Unconstrained)
Increase
US 75 @ Midpark Drive
240,000 vpd
420,000 vpd
75%
US 75 @ Bethany Drive
170,000 vpd
325,000 vpd
90%
* The corridor study will evaluate all feasible and prudent alternatives within the study area including additional freeway lanes, new ma...