File #: 16-175    Name: Ash Woods Construction Budget Amendment
Type: Ordinance Status: Approved
In control: City Council Regular Meeting
On agenda: 2/16/2016 Final action: 2/16/2016
Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2015-2016 Annual Budget and Amending the 2016 - 2020 Capital Improvements Program, to Provide Funds for the Ash Woods Park Pedestrian Bridge Project (PK4368)
Attachments: 1. Ordinance
Title
Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2015-2016 Annual Budget and Amending the 2016 - 2020 Capital Improvements Program, to Provide Funds for the Ash Woods Park Pedestrian Bridge Project (PK4368)

Summary

COUNCIL GOAL: Financially Sound Government

MEETING DATE: February 16, 2016

DEPARTMENT: Parks and Recreation Department

CONTACT: Rhoda L. Savage, Director of Parks and Recreation



RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Ordinance.

ITEM SUMMARY:
* This Ordinance amends the FY2015-2016 annual CIP budget and the 2016 - 2020 Capital Improvement Program, by increasing the budget by $48,320 by transferring $24,160 from the Parkland Dedication Zone 3 Fund and $24,160 for ISD Contributions to the Parks Construction Fund and appropriating the funds to CIP project PK4368 Ash Woods Park Hike and Bike Trail Bridge Project.

BACKGROUND INFORMATION:
* Project design and bidding have been completed.

* The ability to award the bid is contingent on amending the project budget as proposed.

* Through an associated Interlocal Agreement (ILA), the cities of McKinney, Frisco and the Frisco Independent School District agreed to a joint project to construct pedestrian walkways and a pedestrian bridge over an existing drainage swale in Ash Woods Park.

* McKinney's agreed portion of the project was estimated to cost $160,000, of which FISD will fund half. The following is the breakdown of the estimated cost.






City 50% share
FISD 50% share
Estimated Consultant Fee
$ 40,000.00
$ 20,000.00
$ 20,000.00
Estimated Construction Fee
$ 120,000.00
$ 60,000.00
$ 60,000.00
Estimated Budget
$ 160,000.00
$ 80,000.00
$ 80,000.00

* The actual cost is $208,320 with the break down as follows:
Actual Cost

City 50% share
FISD 50% share
Architectural and Engineerin...