File #: 15-953    Name: Lake Forest 5&6 Construction
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 10/6/2015 Final action: 10/6/2015
Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract and All Necessary Change Orders with McMahon Contracting, L.P. for the Construction of Lake Forest Drive Lanes 5 and 6 from SH 121 to McKinney Ranch Parkway
Attachments: 1. Resolution, 2. Location Map, 3. Award Letter
Title
Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract and All Necessary Change Orders with McMahon Contracting, L.P. for the Construction of Lake Forest Drive Lanes 5 and 6 from SH 121 to McKinney Ranch Parkway

Summary

COUNCIL GOAL: Direction for Strategic Growth

MEETING DATE: October 6, 2015

DEPARTMENT: Development Services / Engineering

CONTACT: Gary Graham, PE, CIP & Transportation Engineering Manager
Blake Sills, PE, CIP Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution

ITEM SUMMARY:
* This Resolution authorizes the Interim City Manager to execute a contract and all necessary change orders with McMahon Contracting, LP for the construction of Lake Forest Drive Lanes 5 and 6 from SH 121 to McKinney Ranch Parkway for a total contract amount not to exceed $1,970,000.

BACKGROUND INFORMATION:
* Civil Consulting Group, PLLC, prepared the construction plans for this project.
* No right-of-way was acquired for this project as the two additional lanes on Lake Forest Drive will be constructed in the existing median.
* Five bids were received for this project on July 23, 2015. The following is a summary of the bids:
Bid No.
Bidder
Bid Amount|1313|McMahon Contracting, LP
$1,788,710.62|1313|Tiseo Paving Company
$1,790,920.74|1313|Mario Sinacola & Sons, Excavating
$1,851,006.37|1313|Pavecon
$1,878,538.41|1313|Accelerated Critical Path, Inc.
$2,097,512.90

* McMahon Contracting, LP submitted the low bid in the amount of $1,788,710.62.
* McMahon Contracting, LP submitted references and qualifications that were verified in accordance with the bid specifications.
* The contract documents require that this project be completed within 240 calendar days after issuance of the Notice to Proceed, which is expected in October. Construction is expected to be complete in June 2016.

FINANCIAL SUMMARY:
* This Resolution authorizes a contract and all necessary change orders with...