File #: 15-946    Name: Amending CIP Laud Howell Pkwy
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 10/6/2015 Final action: 10/6/2015
Title: Consider/Discuss/Act on a Resolution Amending the 2016-2020 Capital Improvements Program to Provide Funds for the Engineering Design of Lanes 3 and 4 of Trinity Falls Parkway from Laud Howell Parkway Extending Approximately 1,500 Feet East
Attachments: 1. Resolution, 2. Location Map

Title

Consider/Discuss/Act on a Resolution Amending the 2016-2020 Capital Improvements Program to Provide Funds for the Engineering Design of Lanes 3 and 4 of Trinity Falls Parkway from Laud Howell Parkway Extending Approximately 1,500 Feet East 

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic Growth

 

MEETING DATE:                     October 6, 2015

 

DEPARTMENT:                      Development Services/Engineering

 

CONTACT:                       Mark Hines, PE, Director of Engineering

                     Gary Graham, PE, PTOE, CIP and Traffic Manager

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approval of Resolution

 

ITEM SUMMARY: 

                     This resolution amends the FY2015-2016 Annual Budget and the 2016-2020 Capital Improvements Program by creating a new Capital Improvements Project called ST4422 Trinity Falls Parkway Lanes 3 and 4.

                     The new project will be funded with Funds from the following project:

o                     Transferring $90,000 from ST4373 Development Catalyst Project to the Unallocated Fund Balance ST0000.

o                     Appropriating $90,000 from the Unallocated Fund Balance ST0000 for ST4422 Trinity Falls Parkway Lanes 3 and 4.

 

BACKGROUND INFORMATION: 

                     The City of McKinney has an agreement with Castle Hills, the developer of Trinity Falls, where Castle Hills is required to construct Trinity Falls from FM 543 south approximately 6000 feet.

                     Trinity Falls Parkway will be constructed with four lanes with a median.

                     The existing connection between Laud Howell Parkway and the end of the proposed expansion of Trinity Falls was constructed as two lanes.

                     The approximate length of the additional two lanes to be constructed is 1,500 feet.

 

FINANCIAL SUMMARY: 

                     With the approval of this item, $2,910,000 will remain in ST4373 Developer Catalyst Project.

 

BOARD OR COMMISSION RECOMMENDATION:

                     N/A