File #: 20-0023    Name: Redbud 850PP Transmission Line - Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 1/7/2020 Final action: 1/7/2020
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Excel Aircraft LLC (DBA: Excel Trenching) for the Construction of the Redbud Pump Station Transmission Line (850PP) Phase 2 Project (WA4340) and Any Necessary Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map, 3. Letter of Recommendation
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Excel Aircraft LLC (DBA: Excel Trenching) for the Construction of the Redbud Pump Station Transmission Line (850PP) Phase 2 Project (WA4340) and Any Necessary Supplemental Agreements

Summary

COUNCIL GOAL: Direction for Strategic and Economic Growth
(1A: Establish regional and infrastructure incentives to increase economic growth)

MEETING DATE: January 7, 2020

DEPARTMENT: Development Services / Engineering

CONTACT: Nick Ataie, PE, Engineering CIP Manager
Blake Sills, PE, CIP Project Manager


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with Excel Aircraft LLC (DBA: Excel Trenching) for the construction of the Redbud Pump Station Transmission Line (850PP) Phase 2 Project for a total contract amount not to exceed $3,150,000.

BACKGROUND INFORMATION:
* BGE, Inc. prepared the design and associated construction plans for the Redbud Pump Station Transmission Line (850PP) Phase 2 Project (WA4340).
* The project includes the construction of 4,670 feet of master-planned 42" water transmission line from the Redbud Pump Station to the intersection of Bloomdale Road and Community Avenue.
* The proposed water transmission line will deliver water from the new Redbud Pump Station facility (expected to be operational in early 2020) to the City's 850 water service area.
* On Friday, November 22, 2019, the Purchasing Department opened bids for the project. Six (6) bids were received for Bid No. 20-11CC. The following is a summary of the bids:
Bid No.
Bidder
Bid Amount|1010|Excel Aircraft LLC (DBA: Excel Trenching)
$2,851,121.00|1010|McKee Utility Contractors, Inc.
$3,359,700.00|1010|S.J. Louis Construction of Texas, Ltd.
$3,411,184.30|1010|Thalle Construction Co., Inc.
$3,760,573.00|1010|BELT Construction, Inc.
$4,600,238.00|1010|Texas Standar...

Click here for full text