Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All necessary Change Orders with Ragle, Inc., for the construction of the Collin McKinney Parkway (Lake Forest Drive to Tina Drive) Project
Summary
COUNCIL GOAL: Direction for Strategic and Economic Growth
(1A: Establish regional and infrastructure incentives to increase economic growth)
Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)
MEETING DATE: November 1, 2022
DEPARTMENT: Development Services / Engineering
CONTACT: Blake Sills, PE, Interim Engineering CIP Manager
Aniswarie Kanamazina, PE, CIP Engineer
RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with Ragle, Inc., for the construction of the Collin McKinney Parkway (Lake Forest Drive to Tina Drive) Project (ST1841) for a total contract amount not to exceed $10,650,000.00.
BACKGROUND INFORMATION:
* Kimley-Horn and Associates, Inc. prepared the construction plans for the Collin McKinney Parkway (Lake Forest Drive to Tina Drive) Project (ST1841).
* Collin McKinney Parkway is currently identified as a four-lane divided greenway arterial (G4D Classification) per the Master Thoroughfare Plan.
* The project will include construction of the remaining westbound lanes (north side) as well as the proposed eastbound lanes (south side) of the roadway.
* In addition to the roadway extension, the construction will include installation of median lighting along the length of the roadway as well as constructing an eastbound bridge at Cottonwood Creek along with modifications to the existing westbound bridge. A 10-foot trail will also be added along the roadway and under the bridges.
* Construction will also include installation of a traffic signal at the intersection of Collin McKinney Parkway and Hardin Boulevard, an...
Click here for full text