File #: 17-194    Name: Wilson Creek Trail Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 2/21/2017 Final action: 2/21/2017
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of the Wilson Creek Hike and Bike Trail Project
Attachments: 1. Resolution, 2. Bid Tabulation, 3. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of the Wilson Creek Hike and Bike Trail Project

Summary

COUNCIL GOAL: Direction for Strategic and Economic Growth

MEETING DATE: February 21, 2017

DEPARTMENT: Parks and Recreation

CONTACT: Rhoda L. Savage, Director of Parks and Recreation


RECOMMENDED CITY COUNCIL ACTION:
* Approval of the attached Resolution.

ITEM SUMMARY:
* The Wilson Creek Hike and Bike trail project extends the trail from the Wilson Creek Softball Complex to Eldorado Parkway which will eventually lead to the Heard Museum.

* City staff worked with David C. Baldwin, Inc., a landscape architecture firm, preparing the construction plans and specifications as needed for project bidding.

* The project was bid in a manner that fulfills our legal obligations.

* A total of six (6) bids were submitted and accepted.

* North Rock Construction submitted the lowest bid for the construction of the project for an amount of $676,692.15.

BACKGROUND INFORMATION:
* David C. Baldwin, Inc. along with Staff support, recommends awarding the bid to North Rock Construction for the construction of the Wilson Creek Hike and Bike Trail project.

* If approved, the contract allows for construction to begin in March 2017 with a July 2017 deadline for completion.

FINANCIAL SUMMARY:
* The Wilson Creek Hike and Bike Trail project (PK8062) is a FY16-17 Capital Improvements Project.
* Preliminary estimated project design and development costs were budgeted at $886,700.
* In a concurrent CIP Amendment, staff is requesting additional construction funds ($100,000) as needed to pay the full project costs.

* Below is a summary of the costs associated with the project including the additional funds of $100,000.

o Previous Trail section (previously spent) $ 178,550
o Architectural and Engineering Design Fees $ 81,557
o Construction Contract ...

Click here for full text