File #: 00-224SP    Name: Fagan Alternate Screening
Type: Agenda Item Status: Approved
In control: Planning & Zoning Commission
On agenda: 8/28/2012 Final action: 8/28/2012
Title: Conduct a Public Hearing to Consider/Discuss/Act on the Request by Gary and Natalya Fagan, for Approval of the Site Plan for an Alternate Screening Device for a Multi-Family Development, Approximately 0.40 Acres, Located on the East Side of Tennessee Street and Approximately 200 Feet South of Elm Street.
Attachments: 1. PZ Staff Report, 2. Maps, 3. Letter of Intent, 4. Proposed Site Plan, 5. PowerPoint Presentation
Title
Conduct a Public Hearing to Consider/Discuss/Act on the Request by Gary and Natalya Fagan, for Approval of the Site Plan for an Alternate Screening Device for a  Multi-Family Development, Approximately 0.40 Acres, Located on the East Side of Tennessee Street and Approximately 200 Feet South of Elm Street.
 
Summary
 
MEETING DATE:      August 28, 2012
 
DEPARTMENT:       Development Services - Planning
 
CONTACT:        Brandon Opiela, Senior Planner
      
 
APPROVAL PROCESS:  The Planning and Zoning Commission is the final approval authority for the proposed site plan.
 
STAFF RECOMMENDATION: Staff recommends approval of the proposed site plan with the following conditions:
 
1.      The applicant receive approval of a 6 foot tall wood fence along the southern and eastern property lines.
 
APPLICATION SUBMITTAL DATE:      August 10, 2012 (Original Application)
 
ITEM SUMMARY: A site plan for the subject property was previously approved by the Planning and Zoning Commission on April 24, 2001, which proposed 4 multiple family dwelling units to be placed on an approximately 0.40 acre parcel of land. The previously approved masonry screening wall was recently removed, and the applicant is requesting to replace the masonry wall with an alternate screening device (6' tall wood fence) along the southern and eastern property lines. Per Section 146-132 of the Zoning Ordinance, alternate screening devices must be approved by the Planning and Zoning Commission.
 
It is important to note that although the site plan is being approved a second time, the only change to the plan involves the alternate screening device, and has not altered any other site elements previously approved.