Title
Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with North Rock Construction, LLC of Denton, Texas, for the Construction of the McKinney Soccer Complex at Craig Ranch Connector Road Project
Summary
COUNCIL GOAL: Enhance the Quality of Life in McKinney
(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)
(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)
(5E: Develop sustainable quality of life improvements within the City of McKinney)
MEETING DATE: September 10, 2020
DEPARTMENT: Parks and Recreation
CONTACT: Michael Kowski, Director of Parks and Recreation
RECOMMENDED ACTION:
• Approve the recommendation to City Council.
ITEM SUMMARY:
• This park road will provide a connection between two existing parking lots that are to the south and east of the championship field and will greatly improve vehicular flow throughout the complex.
• City staff worked with DCBA on preparing the construction plans and specifications as needed for project bidding.
• Staff recommends awarding the construction bid to North Rock Construction, LLC in an amount of $197,633.03
BACKGROUND INFORMATION:
• A total of 8 bids were received.
• North Rock Construction, LLC submitted the lowest bid for the construction.
• North Rock Construction has completed projects for the City of McKinney in the past, including Dr. Mack Hill Park and various trail projects.
• If approved, construction should begin in this fall with a 60 day contract schedule.
FINANCIAL SUMMARY:
• This project (PK1906) is a FY19-20 Capital Improvements Program funded by MCDC funds and Parkland Dedication Funds Zone 3.
• Upon approval of this item, $1,587,667 remains in the project budget.