COUNCIL GOAL: Direction for Strategic Growth

MEETING DATE: May 5, 2015

DEPARTMENT: Parks, Recreation, and Open Space

CONTACT: Rhoda L. Savage, Director of Parks, Recreation, and Open Space


RECOMMENDED CITY COUNCIL ACTION:
* Approval of the attached Ordinance

ITEM SUMMARY:
* This Ordinance amends the FY 2014-2015 annual CIP budget and the 2015-2019 Capital Improvements Program by:

o Transferring $85,000 from the Parkland Dedication Fund (Zone 3) to the Parks Construction Fund
o Appropriating $85,000 in the Parks Construction Fund is needed to supplement the proposed construction contract for CIP Project PK3230 - Valley Creek Park Retaining Walls project

* Bids for construction of the Valley Creek Park Retaining Walls project (PK3230) have been received. The recommended contract for construction is $301,567 which exceeds the funds available by an amount of $85,000.

* Increased funding in an amount of $85,000 would provide the additional funds needed for the project including the bid award and cost for construction ($286,345) plus a 5% contingency ($15,222).

* A breakdown of total project costs ($360,000), which includes the Budget Amendment, is included herein:

Original CIP PK3230 Budget Funding $ 275,000
Architectural and Engineering Design Fees - 51,435
Construction Materials Testing - 5,998
TDLR Review and Inspection - 1,000
Currently Available PK3230 Funding $ 216,567

Construction Contract for 2L Const., LLC $ 286,345
Approx. 5% Construction Contingency + 15,222
Requested Construction Budget $ 301,567

Requested Construction Award $ 301,567
Currently Available PK3230 Funding - 216,567
Additional Fundin...