File #: 18-674    Name: Redbud McLarry Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 8/6/2018 Final action: 8/6/2018
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with RKM Utility Services, Inc. for the Construction of Redbud Boulevard (ST1612) and McLarry Drive (ST1613) Paving, Sidewalk, and Drainage Improvements Project
Attachments: 1. Resolution, 2. Location Map, 3. Recommendation Letter
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with RKM Utility Services, Inc. for the Construction of Redbud Boulevard (ST1612) and McLarry Drive (ST1613) Paving, Sidewalk, and Drainage Improvements Project

Summary

COUNCIL GOAL: Direction for Strategic and Economic Growth
(1A: Establish regional and infrastructure incentives to increase economic growth)

MEETING DATE: August 6, 2018

DEPARTMENT: Development Services / Engineering

CONTACT: Joshua Cotton, PE, Senior CIP Engineer
Nick Ataie, PE, Engineering CIP Manager


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with RKM Utility Services, Inc. for the construction of Redbud Boulevard (ST1612) and McLarry Drive (ST1613) Paving, Sidewalk, and Drainage Improvements for a total contract amount not to exceed $2,240,000.

BACKGROUND INFORMATION:
* Freese and Nichols, Inc. prepared the construction plans for this project and has provided a bid award recommendation letter.

* Eleven (11) bids were received for this project on June 28, 2018. The following is a summary of the five (5) lowest bids:

Bid No.
Bidder
Bid Amount
1
RKM Utility Services, Inc.
$1,948,487.20
2
Tiseo Paving Co.
$2,043,202.50
3
Pavecon Public Works, L.P.
$2,120,218.26
4
McMahon Contracting, L.P.
$2,233,272.29
5
Mario Sinacola & Sons Excavating, Inc.
$2,317,059.13

* RKM Utility Services, Inc. submitted the low bid in the amount of $1,948,487.20.

* RKM Utility Services, Inc. submitted references and qualifications that were verified in accordance with the bid specifications.

* The contract documents require that this project be completed within 270 calendar days after issuance of the Notice to Proceed, which is anticipated to be issued by September 2018. Construction is currently anticipated to be complete by May...