File #: 22-0403    Name: McKinney Ranch Pump Station - Materials Testing Contract
Type: Resolution Status: Consent Item
In control: City Council Regular Meeting
On agenda: 5/3/2022 Final action:
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Kleinfelder, Inc. for Materials Testing and Building Systems Commissioning Services on the McKinney Ranch Pump Station Improvements Project (WA1626)
Attachments: 1. Resolution, 2. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Kleinfelder, Inc. for Materials Testing and Building Systems Commissioning Services on the McKinney Ranch Pump Station Improvements Project (WA1626)

Summary

COUNCIL GOAL: Operational Excellence
(2B: Balance available resources to accommodate the growth and maintenance needs of the city)

MEETING DATE: May 3, 2022

DEPARTMENT: Development Services / Engineering

CONTACT: Nick Ataie, PE, Engineering CIP Manager
Paul Tucker, PE, Senior Utility Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract with Kleinfelder, Inc. to provide materials testing and building systems commissioning services during the construction of the McKinney Ranch Pump Station Improvements Project (WA1626), for an amount not to exceed $235,000.

BACKGROUND INFORMATION:
* The construction contract for the McKinney Ranch Pump Station Improvements Project (WA1626) was awarded at the January 18, 2022 City Council meeting.
* Materials testing services will be required on the project to ensure construction materials used by the contractor meet or exceed City requirements.
* Building system commissioning services will be required on the project to ensure the building and building components meet or exceed the City requirements.
* Kleinfelder, Inc. submitted a response to RFQ 21-18 for miscellaneous geotechnical and materials testing services. They were one of five firms shortlisted by City Council on March 16, 2021.
* Kleinfelder, Inc. has successfully performed in a similar capacity on numerous City projects.
* Kleinfelder, Inc. has submitted a proposal for their professional services in the amount of $212,453. This proposal includes materials testing and building systems commissioning services for all phases of construction.
* Reimbursement for materials testing services provided will be made...

Click here for full text