Title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Professional Services Contract with Crossland Construction Company, Inc. whose local office is in Prosper, Texas for Construction Manager at Risk (CMAR) Services Related to the Design and Construction of McKinney Fire Station 11 located at 6260 Rundell Way, McKinney, Texas 75070
Summary
COUNCIL GOAL: Safe and Secure Community
(6A: Maintain Meaningful Public Safety Performance
Measures)
MEETING DATE: February 18, 2020
DEPARTMENT: Fire Department
Public Works Department, Facilities Construction Division
CONTACT: Danny Kistner, Fire Chief
Patricia L. Jackson, PE - Facilities Construction Manager
RECOMMENDED CITY COUNCIL ACTION:
* Approval of the Resolution.
ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a professional services contract with Crossland to provide pre-construction services related to the design and construction of the McKinney Fire Station 11 located at 6260 Rundell Way McKinney, Texas.
* The selected team, Crossland Construction Company, Inc., submitted a proposal to provide pre-construction services for an amount not to exceed $5,000, along with a proposed construction services fee of 3.75% of the cost of construction for Fire Station 11.
BACKGROUND INFORMATION:
* Ten firms submitted statements of qualifications in response to the Request For Qualifications 20-22RFQ and were evaluated by Fire Department staff, the project architect and city staff.
* The top two ranked firms were asked to submit proposals that included pre-construction services fees, construction services fee percentage, costs for general conditions, a proposed project schedule and the like.
* Crossland Construction Company, Inc. was determined to be the top ranked firm after both steps of the CMAR selection process.
* Crossland Construction Company, Inc. is ranked among the top general contractors in the nation, and is among the top 250 largest contra...
Click here for full text