File #: 16-587    Name: Bloomdale Pump Station - Design Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 6/7/2016 Final action: 6/7/2016
Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with Freese & Nichols, Inc. to Provide Consulting Engineering Services for the Bloomdale Road Pump Station Site Development Project and Authorizing Any Supplemental Agreements
Attachments: 1. Resolution, 2. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with Freese & Nichols, Inc. to Provide Consulting Engineering Services for the Bloomdale Road Pump Station Site Development Project and Authorizing Any Supplemental Agreements

Summary

COUNCIL GOAL: Operational Excellence

MEETING DATE: June 7, 2016

DEPARTMENT: Development Services/Engineering

CONTACT: Gary Graham, PE, PTOE, CIP and Traffic Manager
Paul Tucker, PE, Senior Utility Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the Interim City Manager to execute a contract in the amount of $2,413,900, as well as all required supplemental agreements thereto, with Freese & Nichols, Inc. for professional consulting engineering services for the Bloomdale Road Pump Station Site Development Project, for a total aggregate contract amount, inclusive of any supplemental agreements, not to exceed $2,675,000.

BACKGROUND INFORMATION:
* Per the 2012-2013 Water Master Plan, the new pump station facility is needed to provide additional pumping and storage capacity for the growing City population and businesses.
* The City has committed to CH-B Trinity Falls, LP, to use its best efforts to implement the design, construction and make operational the Bloomdale Road Pump Station project in 2018.
* The pump station will provide water supply to potential commercial developments in the Northwest Sector of the City.
* The pump station will have an initial capacity of approximately 20 MGD for the 794 Service Area and 20 MGD for the 850 Service Area. The pump station to be master planned for an ultimate total capacity of 60 MGD (50 MGD firm) for the 794 Service Area and 50 MGD (40 MGD firm) for the 850 Service Area for a future firm capacity of 90 MGD.
* The pump station site will follow the site planning requirements during the master planning and site design process.
* The proj...