File #: 21-0402    Name:
Type: Agenda Item Status: Approved
In control: Parks, Recreation, and Open Space Advisory Board
On agenda: 5/13/2021 Final action: 5/13/2021
Title: Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with Construction Solutions USA, LLC of Carrolton, Texas, for the Construction of the Al Ruschhaupt Park Improvement Project
Title
Consider/Discuss/Act on a Recommendation to City Council for a Resolution Authorizing the City Manager to Execute a Contract with Construction Solutions USA, LLC of Carrolton, Texas, for the Construction of the Al Ruschhaupt Park Improvement Project

Summary

COUNCIL GOAL: Enhance the Quality of Life in McKinney
(5A: Create affordable recreational and cultural arts activities for all ages throughout the city)
(5B: Develop Parks strategy to preserve green space for future park land)
(5C: Continue to market and highlight McKinney as a unique destination for residents and visitors alike)
(5E: Develop sustainable quality of life improvements within the City of McKinney)
(5F: Maximize partnerships between the City of McKinney and private industry)



MEETING DATE: May 13, 2021

DEPARTMENT: Parks and Recreation

CONTACT: Michael Kowski, Director of Parks and Recreation


RECOMMENDED ACTION:
* Approve the recommendation to City Council.

ITEM SUMMARY:
* The Al Ruschhaupt Park Improvement project includes a new restroom facility with an attached plaza area and improved flat work with new landscaping.
o The restroom facility will be 1,200 sq in size with 4 sinks and 6 stalls each on the Men's and Women's side with a family restroom included.
o The restroom facility will also include a concession and storage area located on the North end of the facility.
o The facility will include a covered plaza with a stepped down terrace that will allow for movies in the park or team gatherings along with a patron viewing opportunity.
* City staff worked with Kimley - Horn and Associates, Inc. a landscape architecture firm, on preparing the construction plans and specifications as needed for project bidding.

* The project included a base bid and 1 add alternate:

o Alternate 1: Furnish and install wood decking in lieu of steel decking.
o Wood decking would be in lieu of steel decking based off a lead time of 30 weeks.


* Staff recommends awarding the construc...