File #: 13-328    Name: Tennis Complex Budget Amendment
Type: Ordinance Status: Approved
In control: City Council Regular Meeting
On agenda: 4/2/2013 Final action: 4/2/2013
Title: Consider/Discuss/Act on an Ordinance Amending the 2012-2013 Annual Budget, Including the 2013-2017 Capital Improvements Program, from the Park Construction Fund to Project PK5029 for the Tennis Complex at 3253 Alma Road
Attachments: 1. Agenda Item Summary, 2. Ordinance, 3. Budget Spreadsheet
 
Title
Consider/Discuss/Act on an Ordinance Amending the 2012-2013 Annual Budget, Including the 2013-2017 Capital Improvements Program, from the Park Construction Fund to Project PK5029 for the Tennis Complex at 3253 Alma Road
 
Summary
 
MEETING DATE:      April 2, 2013
 
DEPARTMENT:       Parks, Recreation and Open Space Department
 
CONTACT:        Lemuel Randolph, Director of Parks, Recreation and Open Space
 
 
RECOMMENDED CITY COUNCIL ACTION:      
·      Approval of the Ordinance
 
ITEM SUMMARY:  
·      This Ordinance authorizes the addition of $100,000 from the Park Construction Fund balance to CIP Project PK5029 - Tennis Complex to supplement the $150,000 contract amendment.
·      With previous actions and administrative transfers this Budget Amendment will bring the total project costs of CIP Project PK5029 - Tennis Complex, to $3,855,124.
 
BACKGROUND INFORMATION:  
·      Upon approval of this proposed budget amendment, the Total Project Budget for CIP Project PK5029 will be $3,855,124.
·      Additional funding is needed for design services for Phase II and construction for fencing, repairs and enhancements.
 
FINANCIAL SUMMARY:  
·      This Ordinance authorizes a CIP budget amendment, transferring $100,000 from the Park Construction Fund (PK0000) balance to the Tennis Complex Project (PK5029).
 
BOARD OR COMMISSION RECOMMENDATION:
·      On November 8, 2012, the Parks, Recreation and Open Space Advisory Board recommended to City Council that these funds be transferred.