File #: 16-073    Name: Intersection Improvements Custer Road
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 1/19/2016 Final action: 1/19/2016
Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract and All Necessary Change Orders with XIT Paving and Construction, Inc. for the Construction of Intersection Improvements for Custer Road and Fountain View Drive, Custer Road and Stonebridge Drive, and Custer Road and Stacy Road
Attachments: 1. Resolution, 2. Location Map, 3. Award Letter
Title
Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract and All Necessary Change Orders with XIT Paving and Construction, Inc. for the Construction of Intersection Improvements for Custer Road and Fountain View Drive, Custer Road and Stonebridge Drive, and Custer Road and Stacy Road

Summary

COUNCIL GOAL: Direction for Strategic Growth

MEETING DATE: January 19, 2016

DEPARTMENT: Development Services / Engineering

CONTACT: Gary Graham, PE, CIP & Transportation Engineering Manager
Blake Sills, PE, CIP Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the Interim City Manager to execute a contract and all necessary change orders with XIT Paving and Construction, Inc. for the construction of Intersection Improvements for Custer Road and Fountain View Drive, Custer Road and Stonebridge Drive, and Custer Road and Stacy Road for a total contract amount not to exceed $640,000.

BACKGROUND INFORMATION:
* Freese & Nichols, Inc., prepared the construction plans for this project.

* No right-of-way was acquired for this project.

* Two bids were received for this project on December 17, 2015. Following is a summary of the bids:

Bid No.
Bidder
Bid Amount|1313|XIT Paving and Construction, Inc.
$582,335.00|1313|Rebcon, Inc.
$625,731.34

* XIT Paving and Construction, Inc. submitted the low bid in the amount of $582,335.00.

* XIT Paving and Construction, Inc. submitted references and qualifications that were verified in accordance with the bid specifications.

* The contract documents require that this project be completed within 180 calendar days after issuance of the Notice to Proceed, which is expected in February. Construction is expected to be complete in August 2016.

FINANCIAL SUMMARY:
* This Resolution authorizes a contract and all necessary change orders with XIT Paving and Construction, Inc. for an amount not to exce...