File #: 13-1269    Name: Gabe Nesbitt Park Budget Amendment
Type: Ordinance Status: Approved
In control: City Council Regular Meeting
On agenda: 12/17/2013 Final action: 12/17/2013
Title: Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2014 Annual Budget and Amending the 2014 - 2018 Capital Improvements Program, to Provide Funds for the Gabe Nesbitt Park Infrastructure Improvements
Attachments: 1. Ordinance, 2. Budget Amendment
Title
Consider/Discuss/Act on an Ordinance Amending the Fiscal Year 2014 Annual Budget and Amending the 2014 - 2018 Capital Improvements Program, to Provide Funds for the Gabe Nesbitt Park Infrastructure Improvements
 
Summary
 
MEETING DATE:      December 17, 2013
 
DEPARTMENT:       Development Services/Engineering
 
CONTACT:        Gary Graham, PE, PTOE, Transportation Engineering Manager
 
 
RECOMMENDED CITY COUNCIL ACTION:      
·      Approval of Ordinance
 
ITEM SUMMARY:  
·      This Ordinance amends the FY14 annual budget and the 2014 - 2018 CIP budget by transferring the following amounts to a new CIP project named Gabe Nesbitt Park Infrastructure Improvements (CO4271).
o      $250,000 from the Utility Construction Fund;
o      $530,000 from the Street Construction Fund;
o      $330,000 from the Storm Water Construction Fund; and
o      $645,000 from the Parkland Dedication Zone 3.
·      In addition $85,000 from the Reforestation Funds in the General Fund will be used on the project.
·      The total amount project is $1,840,000.
 
BACKGROUND INFORMATION:  
·      In order to prepare Gabe Nesbitt Park for future development
·      This Ordinance creates a new CIP project and provides the funds needed for the completion of the project.
 
FINANCIAL SUMMARY:  
·      The attached financial summary details the transfer of funds from the other funding sources into a new CIP project called Gabe Nesbitt Park Infrastructure Improvements (CO4271).
 
BOARD OR COMMISSION RECOMMENDATION:
·      N/A