File #: 17-316    Name: Hardin/McKinney Ranch Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 3/21/2017 Final action: 3/21/2017
Title: Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with McMahon Contracting, L.P. for the Construction of Hardin Boulevard Lanes 5 & 6 and McKinney Ranch Parkway Improvements
Attachments: 1. Resolution, 2. Location Map
title
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with McMahon Contracting, L.P. for the Construction of Hardin Boulevard Lanes 5 & 6 and McKinney Ranch Parkway Improvements

Summary

COUNCIL GOAL: Direction for Strategic Growth

MEETING DATE: March 21, 2017

DEPARTMENT: Development Services / Engineering

CONTACT: Gary Graham, PE, CIP & Transportation Engineering Manager
Jason Horn, PE, CIP Engineer

RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution.

ITEM SUMMARY:
* This Resolution authorizes the City Manager to execute a contract and all necessary change orders with McMahon Contracting, L.P. for the construction of Hardin Boulevard Lanes 5 & 6 and McKinney Ranch Parkway Improvements for a total contract amount not to exceed $3,700,000.

BACKGROUND INFORMATION:
* CH2M Hill Engineers, Inc. prepared the construction plans for this project.
* Five bids were received for this project on March 2, 2017. The following is a summary of the bids:
Bid No.
Bidder
Bid Amount|1010|McMahon Contracting, L.P.
$3,368,249.16|1010|Pavecon Public Works, L.P.
$3,616,685.81|1010|Ed Bell Construction Company3
$3,449,290.92|1010|Tiseo Paving Co.
$3,764,244.00|1010|RBR Infrastructure & Road, LLC
$3,978,849.25
* McMahon Contracting, L.P. submitted the low bid in the amount of $3,368,249.16.
* McMahon Contracting, L.P. submitted references and qualifications that were verified in accordance with the bid specifications.
* The contract documents require that this project be completed within 240 calendar days after issuance of the Notice to Proceed, which is expected April 3, 2017. Construction is expected to be complete in November 2017.
* No right-of-way is needed along Hardin. Right-of-way acquisition along McKinney Ranch is ongoing and anticipated to be complete by April 3, 2017.

FINANCIAL SUMMARY:
* This Resolution authorizes a contract and all necessary change orders with McMahon Contracting, ...