Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with Drive Construction GC, LLC of Dallas, Texas, for the Construction of the Community Center Patio Project
Attachments: 1. Resolution, 2. Community Center Patio BID TAB

Title

Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract with Drive Construction GC, LLC of Dallas, Texas, for the Construction of the Community Center Patio Project

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic and Economic Growth

 

MEETING DATE:                     May 3, 2016

 

DEPARTMENT:                      Parks and Recreation

 

CONTACT:                       Rhoda L. Savage, Director of Parks and Recreation

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approve the Resolution as proposed.

 

ITEM SUMMARY: 

                     In 2014 funding was approved in the amount of $500,000 for design and construction of enhancements to the Community Center.

 

                     Enhancements included the addition of a covered patio, retaining walls, a rework of the parking lot to provide an accessible handicap space and an accessible route to the facility, and upgrading the restrooms to meet ADA requirements.

 

                     Construction documents were finalized and the project bid in April 2015.

 

                     Only one bid was received for an amount of $1,200,000.

 

                     The bid was rejected.

 

                     Subsequently, staff hired a professional construction cost estimator to review the plans to determine the actual cost associated with the design.

 

                     That estimator indicated the project should cost around $825,000.

 

                      The estimate was divided into two categories:  general construction and ADA related items.

 

                     The project was bid a second time and bids were opened on February 4, 2016.

 

                     A total of three bids were submitted and accepted.

 

                     Drive Construction GC, LLC submitted the lowest bid for the construction of the project (including a base bid of $809,183 and add alternates 1, 2, and 4) for a total amount equal to $878,397.

 

o                     The following add alternate bid items have been included:

                     1. ADA - Additions and Renovations including Pavestone Retaining Wall and Walk = $12,874

                     2. ADA - Additions and Renovations at Small Northeast Patio = $26,273

                     4. ADA - Folding Doors = $30,067

 

BACKGROUND INFORMATION: 

                     Phelps Woods Architects, the PROS Advisory Board, and City staff support recommendation awarding the bid to Drive Construction GC, LLC for the construction of the Community Center patio project.

 

                     If approved, the contract allows for construction to begin in June 2016 with a November 2016 deadline for completion.

 

 

FINANCIAL SUMMARY: 

                     The Community Center patio project (PK4252) is a FY15-16 Capital Improvements Project funded by previously issued bonds in an amount of $500,000.

 

                     In a concurrent CIP Amendment, staff is requesting additional construction funds in the amount of $220,000 to be appropriated from PK4399 Parks Projects (Umbrella), and $350,000 to be appropriated from PK4325 Parks Accessibility.

 

                     Below is a breakdown showing what the new project total budget ($1,070,000) would be if the additional funds of $570,000 are approved.

 

o                     Architectural and Engineering Design Fees                     $     78,250

o                     Independent Construction Estimate                                          $     10,000

o                     Geotechnical/CMT                                                                                                         $     24,000

o                     TDLR Review and Inspection                                                               $       2,500

o                     Construction Contract                                                                                    $   878,397

o                     Contingency                     (approx. 10%)                                                               $     76,853

Total                                                                                                                                                   $1,070,000

 