File #: 16-475    Name: Community Center Patio Budget Amendment
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 5/3/2016 Final action: 5/3/2016
Title: Consider/Discuss/Act on a Resolution Amending the 2016 - 2020 Capital Improvements Program, to Provide Funds for the Community Center Patio Project (PK4252)
Attachments: 1. Resolution

Title

Consider/Discuss/Act on a Resolution Amending the 2016 - 2020 Capital Improvements Program, to Provide Funds for the Community Center Patio Project (PK4252)

 

Summary

 

COUNCIL GOAL:                     Direction for Strategic and Economic Growth

 

MEETING DATE:                     May 3, 2016

 

DEPARTMENT:                      Parks and Recreation Department

                     

CONTACT:                       Rhoda L. Savage, Director of Parks and Recreation

 

 

 

RECOMMENDED CITY COUNCIL ACTION:                     

                     Approve the Resolution as proposed.

 

ITEM SUMMARY: 

                     This Resolution amends the 2016 - 2020 Capital Improvements Program, by increasing the Community Center Patio Project budget, PK4252, by $570,000 by transferring $350,000 from PK4325 Parks Accessibility and $220,000 from PK4399 Project Umbrella.

 

BACKGROUND INFORMATION: 

                     The Community Center Patio Project (PK4252) is a FY14-15 Capital Improvements Project funded by previously issued bonds in an amount of $500,000.

 

                     An additional $100,000 of Park Accessibility funds, PK4325, approved in the FY 14-15 Budget were reserved for the project.

 

                     As part of the FY 15-16 budget process, MCDC allocated an additional amount of $250,000 for the Community Center Patio Project.

 

                     The FY 15-16 MCDC budget also included a Project Umbrella, PK4399, in an amount of $250,000 for use toward any other approved project including the Community Center Patio Project. 

 

                     The Community Center Patio Project was bid in a manner consistent with State Law.

 

                     Three bids were submitted on February 4, 2016 with the lowest construction bid coming in at $878,397 including the base bid and three bid alternates.

 

                     The ability to award the construction bid and utilize the funds available for this project, is contingent on transferring the aforementioned funds into the Community Center Patio Project, PK4352, as noted in the Item Summary.

 

                     An accompanying Resolution to enter into a construction contract is also on this agenda for Council’s consideration.

 

FINANCIAL SUMMARY: 

                     This Resolution amends the FY2015-2016 annual CIP budget and the 2016 - 2020 Capital Improvement Program, by transferring $350,000 of MCDC funding from the PK4325 Parks Accessibility Project and $220,000 of MCDC funding from the PK4399 Project Umbrella for a total of $570,000 to the PK4252 Community Center Patio Project.

BOARD OR COMMISSION RECOMMENDATION:

                     On April 28, 2016 the MCDC approved reallocation of the $220,000 from the Project Umbrella to the Community Center Patio Project. 

                     The use of $100,000 and $250,000 from the Parks Accessibility Project was approved by the MCDC as part of the Community Center Patio Project during the FY 14-15 and FY15-16 budget process, respectively.