File #: 16-664    Name: Lake Forest Extension Construction Contract
Type: Resolution Status: Approved
In control: City Council Regular Meeting
On agenda: 6/21/2016 Final action: 6/21/2016
Title: Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract and All Necessary Change Orders with Mario Sinacola and Sons Excavating, Inc. for the Construction of Lake Forest Drive Extension from Wilmeth Road to Bloomdale Road
Attachments: 1. Resolution, 2. Location Map
Title
Consider/Discuss/Act on a Resolution Authorizing the Interim City Manager to Execute a Contract and All Necessary Change Orders with Mario Sinacola and Sons Excavating, Inc. for the Construction of Lake Forest Drive Extension from Wilmeth Road to Bloomdale Road

Summary

COUNCIL GOAL: Direction for Strategic & Economic Growth

MEETING DATE: June 21, 2016

DEPARTMENT: Development Services / Engineering

CONTACT: Gary Graham, PE, PTOE, CIP and Traffic Manager
Joshua Cotton, PE, Senior CIP Engineer


RECOMMENDED CITY COUNCIL ACTION:
* Approval of Resolution

ITEM SUMMARY:
* This Resolution authorizes the Interim City Manager to execute a contract and all necessary change orders with Mario Sinacola and Sons Excavating, Inc. for the construction of Lake Forest Drive Extension from Wilmeth Road to Bloomdale Road (ST6093) for a total contract amount not to exceed $4,200,000.

BACKGROUND INFORMATION:
* RLK Engineering, Inc., prepared the construction plans for this project.

* Three (3) bids were received for this project on June 9, 2016. The following is a summary of the bids:

Bid No.
Bidder
Bid Amount|1313|Mario Sinacola and Sons Excavating, Inc.
$3,743,175.45|1313|McMahon Contracting, L.P.
$3,788,811.13|1313|Tiseo Paving Company
$4,610,329.20

* Mario Sinacola and Sons Excavating, Inc. submitted the low bid in the amount of $3,743,175.45.

* Mario Sinacola and Sons Excavating, Inc. submitted references and qualifications that were verified in accordance with the bid specifications.

* The contract documents require that this project be completed within 270 calendar days after issuance of the Notice to Proceed, which is expected to be issued by the end of July. Construction is expected to be complete by May 2017.

* Right-of-way and easements were acquired for this project in order to construct the two northbound lanes of Lake Forest Drive from Wilmeth Road to Bloomdale Road and a portion of Bloomdale Road east of Lake For...

Click here for full text